单选题A resource was dynamically assigned to an LPAR. The customer wants to make the assignment permanent.  What does the technical specialist need to do to reconfigure the LPARs to make the assignment permanent?()A Reboot the source LPAR.B Remove the resour

题目
单选题
A resource was dynamically assigned to an LPAR. The customer wants to make the assignment permanent.  What does the technical specialist need to do to reconfigure the LPARs to make the assignment permanent?()
A

Reboot the source LPAR.

B

Remove the resource from the source LPAR.

C

Rediscover the managed system from the HMC.

D

Add the resource to the profile of the LPAR.


相似考题
更多“单选题A resource was dynamically assigned to an LPAR. The customer wants to make the assignment permanent.  What does the technical specialist need to do to reconfigure the LPARs to make the assignment permanent?()A Reboot the source LPAR.B Remove the resour”相关问题
  • 第1题:

    Company.com wants to reassign a host bus adapter (HBA) from one partition to another to  handle increased I/O workload on that partition. What needs to be done to dynamically move the card?()

    • A、Use the rmdev command to remove the card from the current partition before doing the DLPAR process.
    • B、Take the source partition down and do the DLPAR function on the target partition.
    • C、Assign the card to the required section of the target partition and run cfgmgr.
    • D、Dynamically remove the card from the source and add to target profile then reactivate the target profile.

    正确答案:A

  • 第2题:

    Company.com has ordered an 8-way p5-570 and plans to deploy four AIX 5L v5.3 LPARs. The pre-installation system design has all eight processors being placed in the shared processor pool, and four Micro-Partitions being assigned resources from the pool. Prior to the implementation of the system, the customer informs the technical specialist that one of the applications is only supported on AIX 5L 5.2. Which of the following changes to the system design should the technical specialist make to accommodate this change?()

    • A、Create all the partitions as AIX 5.2, each having two dedicated processors.
    • B、Purchase a system with two additional processors that can be assigned to the AIX 5.2 Partition.
    • C、Specify an AIX 5.2 partition using dedicated processors, reducing the number of processors in the shared pool.
    • D、Use the virtual I/O server to manage the disks and network connections removing the need for different levels of device drivers.

    正确答案:C

  • 第3题:

    The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()

    • A、It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.
    • B、It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.
    • C、It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.
    • D、It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

    正确答案:B

  • 第4题:

    When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()

    • A、xSeries specialist,as the customer may have some Intel-based systems.
    • B、Hardware customer engineer,as they will be installing the entire solution.
    • C、Services specialist,as they can provide education recommendations for the entire solution. 
    • D、Storage specialist,as the customer may need disk to store the data and tape to backup the data.

    正确答案:D

  • 第5题:

    The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()

    • A、Service Processor
    • B、Service Director
    • C、Inventory Scout Services
    • D、Service Focal Point

    正确答案:C

  • 第6题:

    单选题
    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()
    A

    Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters

    B

    Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards

    C

    Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot

    D

    Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    What does the “writer say about customer loyalty in the first paragraph?
    A

    Business executives need to know how to generate customer loyalty.

    B

    Many executives believe more investment in customer loyalty means more profit.

    C

    It is necessary for companies to generate customer loyalty at all costs.

    D

    Customer loyalty will for sure help corporations make more money.


    正确答案: D
    解析:
    第一段第三句指出“Win loyalty, therefore, and profits will follow…”,随后第五行提到“…many business executives agree”,与选项B(很多总裁相信对顾客忠诚度投资越多利润就越多)表达内容相符。

  • 第8题:

    单选题
    The pSeries technical specialist has been invited to a briefing on the latest POWER technology as a representative of their team.  What should the specialist offer to do upon return from class in order to best prepare the rest of the team for the introduction of the new technology?()
    A

    Archive the materials in the team’s library.

    B

    Act as the sole technical resource for the team.

    C

    Summarize the information and make it available to the team.

    D

    Evaluate the class and recommend attendance to other team members.


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    Tests provide grades, but they also let you know what you need to spend more time()and they help make your new knowledge permanent.
    A

    to study

    B

    study

    C

    studied

    D

    studying


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A bank is interested in technology that will enhance competitiveness and flexibility in the financial trading market by harnessing the typically unused power of idle machines.  The pSeries technical specialist should make the customer aware of which IBM offering?()
    A

    IBM Grid Toolbox

    B

    IBM Capacity on Demand

    C

    IBM Cluster Systems Management

    D

    IBM Global Solutions Directory


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A resource was dynamically assigned to an LPAR. The customer wants to make the assignment permanent.  What does the technical specialist need to do to reconfigure the LPARs to make the assignment permanent?()
    A

    Reboot the source LPAR.

    B

    Remove the resource from the source LPAR.

    C

    Rediscover the managed system from the HMC.

    D

    Add the resource to the profile of the LPAR.


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()
    A

    It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.

    B

    It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.

    C

    It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.

    D

    It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Which IBM resource should be used to validate the results from a Disk Magic study PRIOR topresenting the final storage solution and pricing to a customer?()

    • A、Customer Engineer 
    • B、Storage Sales Specialist 
    • C、Competeline Representative 
    • D、Field Technical Storage Specialist (pre-sales)

    正确答案:D

  • 第14题:

    The pSeries technical specialist has been invited to a briefing on the latest POWER technology as a representative of their team.  What should the specialist offer to do upon return from class in order to best prepare the rest of the team for the introduction of the new technology?()

    • A、Archive the materials in the team’s library.
    • B、Act as the sole technical resource for the team.
    • C、Summarize the information and make it available to the team.
    • D、Evaluate the class and recommend attendance to other team members.

    正确答案:C

  • 第15题:

    Your customer wants to make sure that there are not going to be compatibility issues between a third party HBA connecting to their non-IBM Storage device.  What IBM resource would you start with to determine compatibility?()

    • A、IBM Sizing Guides
    • B、IBM Configuration & Options Guide (COG)
    • C、IBM Standalone Solutions Configuration Tool (SSCT)
    • D、IBM ServerProven

    正确答案:D

  • 第16题:

    A resource was dynamically assigned to an LPAR. The customer wants to make the assignment permanent.  What does the technical specialist need to do to reconfigure the LPARs to make the assignment permanent?()

    • A、Reboot the source LPAR.
    • B、Remove the resource from the source LPAR.
    • C、Rediscover the managed system from the HMC.
    • D、Add the resource to the profile of the LPAR.

    正确答案:D

  • 第17题:

    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()

    • A、Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
    • B、Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
    • C、Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
    • D、Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

    正确答案:D

  • 第18题:

    单选题
    When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()
    A

    xSeries specialist,as the customer may have some Intel-based systems.

    B

    Hardware customer engineer,as they will be installing the entire solution.

    C

    Services specialist,as they can provide education recommendations for the entire solution. 

    D

    Storage specialist,as the customer may need disk to store the data and tape to backup the data.


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()
    A

    Service Processor

    B

    Service Director

    C

    Inventory Scout Services

    D

    Service Focal Point


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Your customer wants to make sure that there are not going to be compatibility issues between a third party HBA connecting to their non-IBM Storage device.  What IBM resource would you start with to determine compatibility?()
    A

    IBM Sizing Guides

    B

    IBM Configuration & Options Guide (COG)

    C

    IBM Standalone Solutions Configuration Tool (SSCT)

    D

    IBM ServerProven


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A: I need to make a hotel reservation for my father.  B: ______
    A

    Why does your father want to stay in a hotel?

    B

    Is your father going abroad?

    C

    But do you know how to make a reservation?

    D

    How about calling the travel agency?


    正确答案: B
    解析:
    A方说:“我需要帮我父亲预订旅馆。” C项“但是你知道如何预订旅馆吗”旨在提醒对方,是B方针对A方话语的恰当反应。

  • 第22题:

    单选题
    Company.com has ordered an 8-way p5-570 and plans to deploy four AIX 5L v5.3 LPARs. The pre-installation system design has all eight processors being placed in the shared processor pool, and four Micro-Partitions being assigned resources from the pool. Prior to the implementation of the system, the customer informs the technical specialist that one of the applications is only supported on AIX 5L 5.2. Which of the following changes to the system design should the technical specialist make to accommodate this change?()
    A

    Create all the partitions as AIX 5.2, each having two dedicated processors.

    B

    Purchase a system with two additional processors that can be assigned to the AIX 5.2 Partition.

    C

    Specify an AIX 5.2 partition using dedicated processors, reducing the number of processors in the shared pool.

    D

    Use the virtual I/O server to manage the disks and network connections removing the need for different levels of device drivers.


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    You have an Exchange Server 2010 organization. You need to use Role Based Access Control (RBAC) to provide a user the ability to manage recipients in a specific organizational unit (OU). What should you do first()?
    A

    Create a new direct role assignment.

    B

    Create a new management role assignment policy.

    C

    Create a new management scope.

    D

    Modify the default management scope.


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    Company.com wants to reassign a host bus adapter (HBA) from one partition to another to  handle increased I/O workload on that partition. What needs to be done to dynamically move the card?()
    A

    Use the rmdev command to remove the card from the current partition before doing the DLPAR process.

    B

    Take the source partition down and do the DLPAR function on the target partition.

    C

    Assign the card to the required section of the target partition and run cfgmgr.

    D

    Dynamically remove the card from the source and add to target profile then reactivate the target profile.


    正确答案: D
    解析: 暂无解析