单选题Which feature of the IBM p5 servers enables customers to be confident that data within two distinct partitions on the server will be isolated?()A POWER HypervisorB Virtual LANC POWER5 processorD Redundant Power and Cooling

题目
单选题
Which feature of the IBM p5 servers enables customers to be confident that data within two distinct partitions on the server will be isolated?()
A

POWER Hypervisor

B

Virtual LAN

C

POWER5 processor

D

Redundant Power and Cooling


相似考题
参考答案和解析
正确答案: B
解析: 暂无解析
更多“单选题Which feature of the IBM p5 servers enables customers to be confident that data within two distinct partitions on the server will be isolated?()A POWER HypervisorB Virtual LANC POWER5 processorD Redundant Power and Cooling”相关问题
  • 第1题:

    A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

    • A、p5 hardware, AIX 5.2, Virtual I/O Server
    • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
    • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
    • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

    正确答案:C

  • 第2题:

    A customer has requested five rack mounted servers, and a rack. They want redundant power connections. Which of the following is required to meet these requirements?()

    • A、Redundant power supplies on the servers
    • B、Redundant PDUs in the rack
    • C、edundant power supplies in the servers and redundant PDUs in the rack
    • D、Redundant power supplies in the servers, redundant PDUs in the rack, and Active Energy Manager (AEM)

    正确答案:C

  • 第3题:

    Micro-Partitioning can be defined as().

    • A、multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/2 of a physical processor's resource. 
    • B、multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/100th of a physical processor's resource. 
    • C、an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.3 that allows multiple partitions to share the processing power of a set of physical processors. 
    • D、an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.2 or 5.3 that allows multiple partitions to share the processing power of a set of physical processors.

    正确答案:C

  • 第4题:

    The administrator of a Power 595 server is required to concurrently host LPARs for two different customers. Both customers’ LPARs have the same VLAN ID and subnet range, but their traffic must be isolated from each other.  Which feature within the system would provide this functionality?()

    • A、 802.1Q
    • B、 Virtual switch
    • C、 Logical Host Ethernet (LHE) Adapter
    • D、 Shared Ethernet Adapter (SEA) Trunking

    正确答案:B

  • 第5题:

    Which of the following steps should be done FIRST when deploying a Virtual I/O server on a p5-550, which will host three logical partitions: a NIM server and two application servers?()

    • A、Create and install the NIM server
    • B、Create and install the Virtual I/O Server
    • C、Create and install the application servers
    • D、Activate Advanced POWER Virtualization

    正确答案:D

  • 第6题:

    A customer plans to consolidate to high-end enterprise level servers using multiple partitions.  They are evaluating an IBM POWER5 solution for their server consolidation environment.  Which of the following best describes the value of the IBM solution as compared with the competition?()

    • A、The POWER5 system has greater memory and processor granularity and can also run both Linux and AIX at the same time in different LPARs.
    • B、The POWER5 system supports more partitions, processors, and memory than any competitor’s solution.
    • C、The POWER5 system has the lowest partitioning overhead and can also run both Linux and AIX at the same time in different LPARs.
    • D、The POWER5 system supports more partitions and has the lowest partitioning overhead.

    正确答案:A

  • 第7题:

    单选题
    A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server. Which action will reduce the potential vendor software costs?()
    A

    Create capped partitions for the database servers.

    B

    Create workload partitions for the database servers.

    C

    Create a separate shared processor pool for the database servers.

    D

    Create virtual processors equal to the entitlement for database servers.


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    Which of the following is the BEST case scenario for power fault tolerance within a server?()
    A

     Redundant power supplies with one power supply connected and one power supply as a hot spare.

    B

     Redundant power supplies with each connected to a separate power circuit.

    C

     Redundant power supplies connected via a Y-cable.

    D

     Redundant power supplies with each connected to the same power circuit.


    正确答案: A
    解析: 暂无解析

  • 第9题:

    单选题
    The administrator of a Power 595 server is required to concurrently host LPARs for two different customers. Both customers’ LPARs have the same VLAN ID and subnet range, but their traffic must be isolated from each other.  Which feature within the system would provide this functionality?()
    A

     802.1Q

    B

     Virtual switch

    C

     Logical Host Ethernet (LHE) Adapter

    D

     Shared Ethernet Adapter (SEA) Trunking


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    What is the minimum version of POWER architecture which supports capped and uncapped partitions in the same shared processor pool?()
    A

     POWER4 

    B

     POWER5 

    C

     POWER6 

    D

     POWER5+


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    Which of the following steps should be done FIRST when deploying a Virtual I/O server on a p5-550, which will host three logical partitions: a NIM server and two application servers?()
    A

    Create and install the NIM server

    B

    Create and install the Virtual I/O Server

    C

    Create and install the application servers

    D

    Activate Advanced POWER Virtualization


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()
    A

    Configure a Shared Ethernet Adapter on the Virtual I/O Server.

    B

    Use the same virtual LAN ID on each LPAR.

    C

    Set up IP routing through an LPAR on each system.

    D

    Set up an IP firewall through an LPAR on each system.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()

    • A、Include a new HMC in the order to connect to the p5 595
    • B、Include a pair of new HMCs in the order to connect to the p5 595
    • C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities
    • D、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

    正确答案:B

  • 第14题:

    Company.com has purchased a 2-way p5-520 and would like to create three Micro-Partitions on the server. Which feature of Advanced POWER Virtualization would allow them to create the desired number of partitions?()

    • A、Virtual Ethernet
    • B、Shared Ethernet Adapter
    • C、Dedicated Processors
    • D、Shared Processor Pool

    正确答案:D

  • 第15题:

    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()

    • A、Configure a Shared Ethernet Adapter on the Virtual I/O Server.
    • B、Use the same virtual LAN ID on each LPAR.
    • C、Set up IP routing through an LPAR on each system.
    • D、Set up an IP firewall through an LPAR on each system.

    正确答案:A

  • 第16题:

    What is the minimum version of POWER architecture which supports capped and uncapped partitions in the same shared processor pool?()

    • A、 POWER4 
    • B、 POWER5 
    • C、 POWER6 
    • D、 POWER5+

    正确答案:B

  • 第17题:

    Which of the following best describes Simultaneous Multi-threading (SMT)?()

    • A、A POWER5 microprocessor feature that allocates two processors to each application
    • B、A Workload Manager feature that allows two processing threads to be executing on a single processor
    • C、An AIX v5.2 feature that allows two processing threads to be executing on a single processor concurrently
    • D、A POWER5 microprocessor feature that allows two processing threads to be executing on a single processor concurrently

    正确答案:D

  • 第18题:

    单选题
    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()
    A

    Include a new HMC in the order to connect to the p5 595

    B

    Include a pair of new HMCs in the order to connect to the p5 595

    C

    Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities

    D

    Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities


    正确答案: B
    解析: 暂无解析

  • 第19题:

    单选题
    A customer has requested five rack mounted servers, and a rack. They want redundant power connections. Which of the following is required to meet these requirements?()
    A

    Redundant power supplies on the servers

    B

    Redundant PDUs in the rack

    C

    edundant power supplies in the servers and redundant PDUs in the rack

    D

    Redundant power supplies in the servers, redundant PDUs in the rack, and Active Energy Manager (AEM)


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A customer plans to consolidate to high-end enterprise level servers using multiple partitions.  They are evaluating an IBM POWER5 solution for their server consolidation environment.  Which of the following best describes the value of the IBM solution as compared with the competition?()
    A

    The POWER5 system has greater memory and processor granularity and can also run both Linux and AIX at the same time in different LPARs.

    B

    The POWER5 system supports more partitions, processors, and memory than any competitor’s solution.

    C

    The POWER5 system has the lowest partitioning overhead and can also run both Linux and AIX at the same time in different LPARs.

    D

    The POWER5 system supports more partitions and has the lowest partitioning overhead.


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    Which of the following best describes Simultaneous Multi-threading (SMT)?()
    A

    A POWER5 microprocessor feature that allocates two processors to each application

    B

    A Workload Manager feature that allows two processing threads to be executing on a single processor

    C

    An AIX v5.2 feature that allows two processing threads to be executing on a single processor concurrently

    D

    A POWER5 microprocessor feature that allows two processing threads to be executing on a single processor concurrently


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Micro-Partitioning can be defined as().
    A

    multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/2 of a physical processor's resource. 

    B

    multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/100th of a physical processor's resource. 

    C

    an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.3 that allows multiple partitions to share the processing power of a set of physical processors. 

    D

    an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.2 or 5.3 that allows multiple partitions to share the processing power of a set of physical processors.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A small organization is purchasing a POWER5 to consolidate four applications. Currently, each application has two Host Bus Adapters (HBA) connected to an Enterprise Storage Server (ESS). The customer is concerned about the cost of purchasing eight new HBAs. Which feature of virtualization will be most beneficial to this organization?()
    A

    Virtual Ethernet

    B

    Micro-Partitioning

    C

    Virtual I/O Server

    D

    Capped and uncapped partitions


    正确答案: B
    解析: 暂无解析