niusouti.com

单选题In order to upgrade from AIX Version 4.3 to AIX Version 5.2, which of the following actions should be performed?()A Run smit update_allB Run smit install_allC Boot from the installation mediaD Run update_all from the mounted CD

题目
单选题
In order to upgrade from AIX Version 4.3 to AIX Version 5.2, which of the following actions should be performed?()
A

Run smit update_all

B

Run smit install_all

C

Boot from the installation media

D

Run update_all from the mounted CD


相似考题
更多“单选题In order to upgrade from AIX Version 4.3 to AIX Version 5.2, which of the following actions should be performed?()A Run smit update_allB Run smit install_allC Boot from the installation mediaD Run update_all from the mounted CD”相关问题
  • 第1题:

    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()

    • A、IBM Techline
    • B、IBM Supportline
    • C、IBM Software Distribution
    • D、IBM Hardware Support

    正确答案:B

  • 第2题:

    What are the steps required to perform a Preservation install on a server?()

    • A、Shutdown the server and boot it into SMS. Select SMS menu option OS Upgrade, Preservation install for the install type, and allow upgrade to run.
    • B、Shut down the server and perform a network boot from a local NIM server. Select Presevation install for the install type, and allow upgrade to run.
    • C、Shutdown the server and boot it into SMS. Select SMS menu option OS Upgrade, Presevation install for the install type, and allow for upgrade to run.
    • D、Re-boot the server and NFS mount the bos images from a local NIM server. Run smit install. Select Presevation install for the install type, and allow upgrade to run.

    正确答案:A

  • 第3题:

    Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()

    • A、Verify the ISV application runs on AIX 5.2
    • B、Power4 to POWER5 upgrades are not supported without a application recompile
    • C、Check the placement and size of the boot logical volume and disk space requirements on the S85
    • D、AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked

    正确答案:A

  • 第4题:

    A customer has a pSeries that needs to be upgraded from AIX Version 5.1 to AIX Version 5.2. The customer wants to retain /etc/passwd. Which of the following installation types should be used?()

    • A、Preservation Install
    • B、Retention Install
    • C、Overwrite Install
    • D、Migration Install

    正确答案:D

  • 第5题:

    Which of the following actions will allow you to convert from Windows Server 2012 R2 Standard to Windows Server Datacenter, using the least administrative effort?()

    • A、You should run Setup from the installation media.
    • B、You should run the Install-WindowsFeature cmdlet from the Windows PowerShell.
    • C、You should run the dism /online /add-package command from an elevated command prompt.
    • D、You should run the dism /online /enable-feature command from an elevated command Prompt.
    • E、You should run the dism /online /set-edition command from an elevated command prompt.

    正确答案:E

  • 第6题:

    单选题
    A System p administrator needs to upgrade a system from AIX 5.2 to AIX 5.3.  Which of the following installation methods would minimize downtime()
    A

    Migration installation

    B

    Partition Mobility

    C

    alt_disk_install

    D

    update_all smit fastpath and reboot during the next scheduled outage


    正确答案: A
    解析: 暂无解析

  • 第7题:

    单选题
    Which of the following actions will allow you to convert from Windows Server 2012 R2 Standard to Windows Server Datacenter, using the least administrative effort?()
    A

    You should run Setup from the installation media.

    B

    You should run the Install-WindowsFeature cmdlet from the Windows PowerShell.

    C

    You should run the dism /online /add-package command from an elevated command prompt.

    D

    You should run the dism /online /enable-feature command from an elevated command Prompt.

    E

    You should run the dism /online /set-edition command from an elevated command prompt.


    正确答案: C
    解析: 暂无解析

  • 第8题:

    单选题
    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()
    A

    IBM Techline

    B

    IBM Supportline

    C

    IBM Software Distribution

    D

    IBM Hardware Support


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    An administrator has received an update CD with the latest technology level for AIX 5.3. The current  operating system level of the sever is at base AIX5.3.  What action needs to be taken to apply the new  technology level to the server()
    A

    Run smit update_all

    B

    Run smit install_all

    C

    Boot from the installation media

    D

    Run the update_all command from the mounted CD


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A system administrator needs to quickly migrate a machine from AIX 5.1 to AIX 5.2. The administrator will only be allowed enough downtime to reboot the machine. Which installation method should be used to accomplish this task?()
    A

    Perform a migration installation during the reboot process.

    B

    Perform an alternate disk installation and migration using NIM.

    C

    Copy the /usr directory from another 5.2 server to this server.

    D

    Perform an update_all install from 5.2 media to take effect on reboot.


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    A system administrator has a mksysb on tape of an AIX 5.2 machine and needs to install it on a different server. How can this be accomplished?()
    A

    Install the base AIX from 5.2 media and then install the mksysb overtop.

    B

    Mount the tape and use the tar command to install AIX and the rest of the contents of the rootvg.

    C

    Insert the mksysb tape and a 5.2 base media CD and then boot to maintenance mode and initiate the install.

    D

    Install AIX 5.2 from base media and then perform an update_all install from the mksysb tape of the original machine.


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A system was running properly until a reboot. Following the reboot, the system LED displayed cycles between 0223 and 0229. Which of the following procedures should be performed next?()
    A

    Power down then power up the system

    B

    Boot into diagnostic mode and run fsck

    C

    Boot from installation media and run bosboot

    D

    Boot into maintenance mode and check the bootlist


    正确答案: D
    解析: 暂无解析

  • 第13题:

    An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()

    • A、Use the clstat command and verify the cluster is in a stable state
    • B、After each node is upgraded, run a verification and synchronization
    • C、After all nodes are upgraded, run a verification and synchronization
    • D、Take a snapshot of each node and verify the configuration is the same

    正确答案:C

  • 第14题:

    A system administrator needs to quickly migrate a machine from AIX 5.1 to AIX 5.2. The administrator will only be allowed enough downtime to reboot the machine. Which installation method should be used to accomplish this task?()

    • A、Perform a migration installation during the reboot process.
    • B、Perform an alternate disk installation and migration using NIM.
    • C、Copy the /usr directory from another 5.2 server to this server.
    • D、Perform an update_all install from 5.2 media to take effect on reboot.

    正确答案:B

  • 第15题:

    A system was running properly until a reboot. Following the reboot, the system LED displayed cycles between 0223 and 0229. Which of the following procedures should be performed next?()

    • A、Power down then power up the system
    • B、Boot into diagnostic mode and run fsck
    • C、Boot from installation media and run bosboot
    • D、Boot into maintenance mode and check the bootlist

    正确答案:D

  • 第16题:

    A System p administrator needs to upgrade a system from AIX 5.2 to AIX 5.3.  Which of the following installation methods would minimize downtime()

    • A、Migration installation
    • B、Partition Mobility
    • C、alt_disk_install
    • D、update_all smit fastpath and reboot during the next scheduled outage

    正确答案:C

  • 第17题:

    A system administrator has a mksysb on tape of an AIX 5.2 machine and needs to install it on a different server. How can this be accomplished?()

    • A、Install the base AIX from 5.2 media and then install the mksysb overtop.
    • B、Mount the tape and use the tar command to install AIX and the rest of the contents of the rootvg.
    • C、Insert the mksysb tape and a 5.2 base media CD and then boot to maintenance mode and initiate the install.
    • D、Install AIX 5.2 from base media and then perform an update_all install from the mksysb tape of the original machine.

    正确答案:C

  • 第18题:

    单选题
    An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()
    A

    Use the clstat command and verify the cluster is in a stable state

    B

    After each node is upgraded, run a verification and synchronization

    C

    After all nodes are upgraded, run a verification and synchronization

    D

    Take a snapshot of each node and verify the configuration is the same


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    What are the steps required to perform a Preservation install on a server?()
    A

    Shutdown the server and boot it into SMS. Select SMS menu option OS Upgrade, Preservation install for the install type, and allow upgrade to run.

    B

    Shut down the server and perform a network boot from a local NIM server. Select Presevation install for the install type, and allow upgrade to run.

    C

    Shutdown the server and boot it into SMS. Select SMS menu option OS Upgrade, Presevation install for the install type, and allow for upgrade to run.

    D

    Re-boot the server and NFS mount the bos images from a local NIM server. Run smit install. Select Presevation install for the install type, and allow upgrade to run.


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()
    A

    Verify the ISV application runs on AIX 5.2

    B

    Power4 to POWER5 upgrades are not supported without a application recompile

    C

    Check the placement and size of the boot logical volume and disk space requirements on the S85

    D

    AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has a pSeries that needs to be upgraded from AIX Version 5.1 to AIX Version 5.2. The customer wants to retain /etc/passwd. Which of the following installation types should be used?()
    A

    Preservation Install

    B

    Retention Install

    C

    Overwrite Install

    D

    Migration Install


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Which of the following procedures should be performed to run diagnostics in single-user mode? ()
    A

     Run standalone diagnostics from the cd. 

    B

     Run standalone diagnostics from the AIX tape. 

    C

     Run maintenance mode diagnostics from the hard drive. 

    D

     Run maintenance mode diagnostics from the diskette. 


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    What are the steps required to perform a Preservation install on a server?()
    A

    Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade,Preservation install for the install type,and allow upgrade to run

    B

    Shut down the server and perform a network boot from a local NIM server.Select Presevation install for the install type,and allow upgrade to run

    C

    Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade,Presevation install for the install type,and allow for upgrade to run

    D

    Re-boot the server and NFS mount the bos images from a local NIM server.Run smit install.Select Presevation install for the install type,and allow upgrade to run


    正确答案: C
    解析: 暂无解析