niusouti.com

单选题A customer is considering replacement of twenty older 4U and 6U rack-based servers with one IBM x366 Server running VMWare ESX attached to one DS4300.  Which of the following represents a reduction in Total Cost of Ownership (TCO) for the customer?()A

题目
单选题
A customer is considering replacement of twenty older 4U and 6U rack-based servers with one IBM x366 Server running VMWare ESX attached to one DS4300.  Which of the following represents a reduction in Total Cost of Ownership (TCO) for the customer?()
A

Reduction in operating system software licensing and application costs

B

Reduction in floor space and hardware cost saving

C

VMWare is licensed per system so no extra charge for SMP support

D

No single point of failure, reducing downtime


相似考题
更多“单选题A customer is considering replacement of twenty older 4U and 6U rack-based servers with one IBM x366 Server running VMWare ESX attached to one DS4300.  Which of the following represents a reduction in Total Cost of Ownership (TCO) for the customer?()A ”相关问题
  • 第1题:

    A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()

    • A、Ten x306’s with internal SATA drives
    • B、Five x346’s with internal SATA drives and VMWare ESX Server
    • C、Five x366’s partitioned into two VMs each with VMWare ESX Server
    • D、Ten x336’s with internal SATA drives

    正确答案:D

  • 第2题:

    A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()

    • A、What version of VMWare ESX Server is being considered?
    • B、Do the systems currently use Double Data Rate (DDR) memory?
    • C、What is the total number of processors installed in the production systems?
    • D、What is the total amount of memory currently being used across all the production systems?

    正确答案:D

  • 第3题:

    A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers.  Which of the following should the Sales Specialist emphasize to address the pricing difference?()

    • A、Higher rack density that reduces data center footprints
    • B、Internal upgrades that only IBM can offer
    • C、Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches 
    • D、The Rear Door Heat eXchanger that only IBM can offer

    正确答案:C

  • 第4题:

    A customer is in the initial stages of implementing a server consolidation project.  The Information Technology staff has identified several Microsoft Windows servers that are running single applications on older hardware and averaging under 20% utilization.  Part of their server consolidation goal is to lower the number of servers, decrease the operating system license cost, and increase utilization per server.  Which of the following IBM Director extensions could be used to satisfy all of these requirements?()

    • A、Aurema Application Workload Manager
    • B、Remote Deployment Manager
    • C、Virtual Machine Manager
    • D、Capacity Manager

    正确答案:A

  • 第5题:

    A customer needs to deploy a SAN and connect nine servers running a mix of Windows and Linux.  They currently need 12TB, but their growth requirements will be tripled in the near future.  They will also consolidate 18 legacy Windows servers onto one system using virtualization software and connect that server to the storage solution.  A DS4000 series backup solution needs to be included in the design.  Which of the following solutions will satisfy these requirements?()

    • A、DS4300 with a switched fabric and an x445 running VMWare ESX server
    • B、DS4500 with a switched fabric and an x445 running VMWare ESX server
    • C、DS4300 SAN with a switched fabric and an x445 running Microsoft Virtual Server
    • D、DS4400 Server with an x445 running Virtuozzo VPS

    正确答案:B

  • 第6题:

    单选题
    A customer has four 2-way 2U front-end web servers that are currently running at 15% CPU utilization.  These servers provide points of access for users worldwide, and volume is expected to triple in the next six months and aggressively grow thereafter.  They want to upgrade these systems to newer technology and stay within the 8U of rack space that they are replacing.  Which solution would fit the customer’s requirements?()
    A

    Three x366 4-ways running VMWare ESX Server.

    B

    An x445 8-way Xeon MP attached to a DS4300 and running VMWare ESX Server.

    C

    An x445 16-way Xeon MP attached to an EXP400 and running VMWare ESX Server.

    D

    Four x346 2-ways running VMWare ESX Server.


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    A customer is in the initial stages of implementing a server consolidation project.  The Information Technology staff has identified several Microsoft Windows servers that are running single applications on older hardware and averaging under 20% utilization.  Part of their server consolidation goal is to lower the number of servers, decrease the operating system license cost, and increase utilization per server.  Which of the following IBM Director extensions could be used to satisfy all of these requirements?()
    A

    Aurema Application Workload Manager

    B

    Remote Deployment Manager

    C

    Virtual Machine Manager

    D

    Capacity Manager


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    A customer recently purchased a new x3550 M3 server and one of the hard drives has failed. The customer has a standard warranty. They called you asking for a replacement. Which action should the customer take?()
    A

    Contact the IBM FTSS to replace the drive

    B

    Contact the IBM CSR or SSR to replace the drive

    C

    Order a replacement drive

    D

    Contact IBM Service


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    A customer needs to deploy a SAN and connect nine servers running a mix of Windows and Linux.  They currently need 12TB, but their growth requirements will be tripled in the near future.  They will also consolidate 18 legacy Windows servers onto one system using virtualization software and connect that server to the storage solution.  A DS4000 series backup solution needs to be included in the design.  Which of the following solutions will satisfy these requirements?()
    A

    DS4300 with a switched fabric and an x445 running VMWare ESX server

    B

    DS4500 with a switched fabric and an x445 running VMWare ESX server

    C

    DS4300 SAN with a switched fabric and an x445 running Microsoft Virtual Server

    D

    DS4400 Server with an x445 running Virtuozzo VPS


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer is planning to upgrade two VMware ESX servers from 3.5 to 4.1 after recently installing a new XIV Storage System. Each server has 4 HBAs connected to redundant fabrics for a total of 4 paths per server to storage. The customer wants to increase the throughput available to the ESX servers. What configuration setting does the storage specialist need to highlight?()
    A

    increase the buffer credits on the HBAs

    B

    increase the number of device logins on the ESX servers

    C

    additional paths will be required between the servers and storage

    D

    multipath option on the ESX servers should be changed to round-robin


    正确答案: C
    解析: 暂无解析

  • 第11题:

    多选题
    A customer has a mixed Dell and IBM server environment.  They want to implement a system management solution for all their Windows, Linux, and VMWare ESX Intel based servers.  Which TWO features of IBM Director will be an advantage for this customer?()
    A

    IBM Director comes with free Aurema and SteelEye software plug-ins.

    B

    IBM Director supports non-IBM industry standard Intel based servers.

    C

    IBM Director servers can be managed from within the MS Performance Monitor.

    D

    IBM Director requires no agents to be installed and run on the IBM systems.

    E

    IBM Director offers agents to manage VMWare ESX Server and runs on Linux while Dell does not.


    正确答案: B,A
    解析: 暂无解析

  • 第12题:

    单选题
    A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()
    A

    Ten x306’s with internal SATA drives

    B

    Five x346’s with internal SATA drives and VMWare ESX Server

    C

    Five x366’s partitioned into two VMs each with VMWare ESX Server

    D

    Ten x336’s with internal SATA drives


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer wants to deploy VMWare ESX on four-way Intel systems.  They are considering IBM and Dell.Which of the following is an advantage IBM has over the competition?()

    • A、IBM provides optional Remote Technical Support for hardware, NOS, and VMWare.
    • B、The IBM xSeries EXA chipset has extensions to provide better efficiency for the VMFS file system.
    • C、IBM servers can address larger LUNs on SAN storage than Dell.
    • D、IBM provided VMWare with the majority of their internal drivers for ESX.

    正确答案:A

  • 第14题:

    A customer has a mixed Dell and IBM server environment.  They want to implement a system management solution for all their Windows, Linux, and VMWare ESX Intel based servers.  Which TWO features of IBM Director will be an advantage for this customer?()

    • A、IBM Director comes with free Aurema and SteelEye software plug-ins.
    • B、IBM Director supports non-IBM industry standard Intel based servers.
    • C、IBM Director servers can be managed from within the MS Performance Monitor.
    • D、IBM Director requires no agents to be installed and run on the IBM systems.
    • E、IBM Director offers agents to manage VMWare ESX Server and runs on Linux while Dell does not.

    正确答案:B,E

  • 第15题:

    A customer has four 2-way 2U front-end web servers that are currently running at 15% CPU utilization.  These servers provide points of access for users worldwide, and volume is expected to triple in the next six months and aggressively grow thereafter.  They want to upgrade these systems to newer technology and stay within the 8U of rack space that they are replacing.  Which solution would fit the customer’s requirements?()

    • A、Three x366 4-ways running VMWare ESX Server.
    • B、An x445 8-way Xeon MP attached to a DS4300 and running VMWare ESX Server.
    • C、An x445 16-way Xeon MP attached to an EXP400 and running VMWare ESX Server.
    • D、Four x346 2-ways running VMWare ESX Server.

    正确答案:B

  • 第16题:

    The customer is consolidating their ten rack mount Windows servers into a VMware environment with four servers. The existing servers all have internal disk. The total amount of useable capacity is 5TB which is expected to increase to 10TB over the life of this asset. The customer will want to use the advanced features of VMware like VMotion. The customer is concerned about cost. Which of the following meets the customers needs?()

    • A、DS3500 with SAS Host Connection
    • B、DS3500 withiSCSI Host Connection
    • C、DS3500 with FC Connection
    • D、DS5020

    正确答案:A

  • 第17题:

    单选题
    An existing IBM customer has some iSeries servers in their environment.  The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications.  The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms.  Which of the following will accomplish this?()
    A

    Share the data over the Ethernet LAN.

    B

    Install the IXA Adapter in the iSeries server.

    C

    Install the IXA Adapter in the xSeries server.

    D

    Attach both servers to an IXS switch.


    正确答案: C
    解析: 暂无解析

  • 第18题:

    单选题
    The customer is consolidating their ten rack mount Windows servers into a VMware environment with four servers. The existing servers all have internal disk. The total amount of useable capacity is 5TB which is expected to increase to 10TB over the life of this asset. The customer will want to use the advanced features of VMware like VMotion. The customer is concerned about cost. Which of the following meets the customers needs?()
    A

    DS3500 with SAS Host Connection

    B

    DS3500 withiSCSI Host Connection

    C

    DS3500 with FC Connection

    D

    DS5020


    正确答案: D
    解析: 暂无解析

  • 第19题:

    多选题
    A customer is considering consolidating their file servers by moving them into a virtual environment using VMWare ESX Server running on an x445 system.  The ratio of consolidation is expected to be about 15:1.  Which TWO of the Total Cost of Ownership factors are the key benefits of this solution?()
    A

    VMWare is licensed per system so no extra charge for SMP support

    B

    Lowering administration cost while providing better remote management tools

    C

    The x445 provides high availability options designed to minimize system outages

    D

    The x445 provides no single point of failure

    E

    The x445 provides SAN Connectivity right out of the box without needing to purchase extra hardware


    正确答案: A,D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers.  Which of the following should the Sales Specialist emphasize to address the pricing difference?()
    A

    Higher rack density that reduces data center footprints

    B

    Internal upgrades that only IBM can offer

    C

    Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches 

    D

    The Rear Door Heat eXchanger that only IBM can offer


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()
    A

    What version of VMWare ESX Server is being considered?

    B

    Do the systems currently use Double Data Rate (DDR) memory?

    C

    What is the total number of processors installed in the production systems?

    D

    What is the total amount of memory currently being used across all the production systems?


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer wants to deploy VMWare ESX on four-way Intel systems.  They are considering IBM and Dell.Which of the following is an advantage IBM has over the competition?()
    A

    IBM provides optional Remote Technical Support for hardware, NOS, and VMWare.

    B

    The IBM xSeries EXA chipset has extensions to provide better efficiency for the VMFS file system.

    C

    IBM servers can address larger LUNs on SAN storage than Dell.

    D

    IBM provided VMWare with the majority of their internal drivers for ESX.


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    A customer is running system management software on one of their Windows xSeries servers, and the software seems to slow down their database application over time.  The customer is running IBM Director in their environment.  Which IBM Director tool can they utilize to guarantee processor time for the different applications and optimize the server performance?()
    A

    Software Rejuvenation

    B

    Capacity Manager

    C

    Capacity Workload Manager

    D

    Aurema Application Workload Manager


    正确答案: D
    解析: 暂无解析