单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A Evaluate phase exit

题目
单选题
The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
A

Evaluate phase exit milestones using sufficiency criteria

B

Flexible entry and exit criteria to minimize schedule delays

C

Quality measures reported only to the project steering committee

D

Many work teams with few members to maximize the number of deliverable hand-offs


相似考题
参考答案和解析
正确答案: C
解析: 暂无解析
更多“单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A Evaluate phase exit”相关问题
  • 第1题:

    By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A Significantly reduce project risks

    B eliminate project risks

    C provide a rational basis for better decision making

    D identify risks, their impact(s), and any appropriate responses

    E None of the above.


    正确答案:B

  • 第2题:

    59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A. Significantly reduce project risks

    B. eliminate project risks

    C. provide a rational basis for better decision making

    D. identify risks, their impact(s), and any appropriate responses

    E. None of the above


    正确答案:B

  • 第3题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    A.Project

    B.project management team

    C.performingorganization

    D.customer


    参考答案:C

    该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第4题:

    ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C

  • 第5题:

    ●The quality management plan should describe how the project management team will implement its quality (73).

    (73) A. improvement

    B. control

    C. policy

    D. information


    正确答案:C

  • 第6题:

    The quality management plan should describe how the project management team will implement its quality(73).

    A. improvement

    B. control

    C. policy

    D. information


    正确答案:C
    质量管理计划应说明项目管理团队如何来实施执行其质量。(73)A.改进B.控制C.政策D.信息。

  • 第7题:

    The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality),(), and cost.

    A.resource

    B.time

    C.plan

    D.tool


    正确答案:B

  • 第8题:

    ( )The process of translating the quality management plan into eecutable quality activities that incorporate the organization's quality policies into the project.

    A:Munage quality
    B:Quality audit
    C:Quality metrics
    D:Quality improvement

    答案:C
    解析:

  • 第9题:

    ( )in not inc1uded in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告

  • 第10题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第11题:

    单选题
    Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
    A

    performance

    B

    process

    C

    product

    D

    object


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
    A

    Project

    B

    project management team

    C

    performingorganization

    D

    customer


    正确答案: B
    解析: 该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第13题:

    41 In the project environment, the individual ultimately responsible for quality control is:

    A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D. The project manager who has ultimate responsibility for the entire project.

    E.the customer who must ensure that he is receiving a quality product from the vendor


    正确答案:D

  • 第14题:

    69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

    A. budget, schedule

    B. quality requirements, schedule

    C. size, type of industry

    D. nature, size

    E. project manager, sponsor


    正确答案:D

  • 第15题:

    ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A The project manager and project office personnel.

    B The project team and functional managers.

    C The project sponsor.

    D All of the above.

    E A and B only.


    正确答案:E

  • 第16题:

    Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


    正确答案:C

    项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第17题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第18题:

    The quality management plan should describe how the project management team will implement its quality(73).

    A.improvement

    B.control

    C.policy

    D.information


    正确答案:C
    质量管理计划应说明项目管理团队如何来实施执行其质量(73)。A.改进B.控制C.政策D.信息。

  • 第19题:

    Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C
    解析:项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第20题:

    ( )is not included in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告。

  • 第21题:

    Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

    • A、performance
    • B、process
    • C、product
    • D、object

    正确答案:B

  • 第22题:

    The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()

    • A、Evaluate phase exit milestones using sufficiency criteria
    • B、Flexible entry and exit criteria to minimize schedule delays
    • C、Quality measures reported only to the project steering committee
    • D、Many work teams with few members to maximize the number of deliverable hand-offs

    正确答案:A

  • 第23题:

    单选题
    Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
    A

    performance

    B

    process

    C

    product

    D

    object


    正确答案: D
    解析: 该题的关键词为"Project Quality Management、product quality measures and techniques"。题干包含三个单独的语句,但其逻辑关联紧密,可注意到后两句是对前一句的补充说明,其语句结构分别为"Project Quality Management(主语)must address(谓语)","Project Quality Management(主语)applies(谓语)to all projects","product quality measures and techniques(主语) are specific(谓语)to the particulartype of product produced by the project",首句说明项目质量管理必须关注项目的管理以及项目什么的管理,后两句则说明项目生成的特定产品的度量与技术因产品的不同而有差异。根据语句的逻辑关系,应该选择选项C。

  • 第24题:

    单选题
    The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
    A

    Evaluate phase exit milestones using sufficiency criteria

    B

    Flexible entry and exit criteria to minimize schedule delays

    C

    Quality measures reported only to the project steering committee

    D

    Many work teams with few members to maximize the number of deliverable hand-offs


    正确答案: D
    解析: 暂无解析