单选题Which factor has the greatest impact on the estimated per unit labor cost for a project?()A Historical informationB Use of outside vendorsC Change control processesD Human resource skill level requirements

题目
单选题
Which factor has the greatest impact on the estimated per unit labor cost for a project?()
A

Historical information

B

Use of outside vendors

C

Change control processes

D

Human resource skill level requirements


相似考题
更多“单选题Which factor has the greatest impact on the estimated per unit labor cost for a project?()A Historical informationB Use of outside vendorsC Change control processesD Human resource skill level requirements”相关问题
  • 第1题:

    By which means is a contractor able to control cost overruns due to changing requirements?

    A Project data review

    B Change order

    C Purchase order amendment

    D Change control

    E None of the above.


    正确答案:D

  • 第2题:

    19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A. Direct labor dollars

    B. Direct labor hours.

    C. Overhead rates.

    D. Procurement costs.

    E. None of the above


    正确答案:B

  • 第3题:

    151 Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A. Past project records (historical data)

    B. Commercial techniques (standard practices, rules of thumb)

    C. Past project team members knowledge (experience, oldtimers)

    D. All of the above

    E. A and C only


    正确答案:D

  • 第4题:

    2 Ice-Time Ltd (ITL) manufactures a range of sports equipment used in a variety of winter-sports in Snowland.

    Development engineers within ITL have recently developed a prototype of a small engine-propelled bobsleigh named

    the ‘Snowballer’, which has been designed for use by young children. The directors of ITL recently spent £200,000

    on market research, the findings of which led them to believe that a market exists for the Snowballer.

    The marketing director has suggested that ITL should use the ‘Olympic’ brand in order to market the Snowballer.

    The finance director of ITL has gathered relevant information and prepared the following evaluation relating to the

    proposed manufacture and sale of the Snowballer.

    (1) Sales are expected to be 3,200 units per annum at a selling price of £2,500 per unit.

    (2) Variable material, labour, and overhead costs are estimated at £1,490 per unit.

    (3) In addition, a royalty of £150 per unit would be payable to Olympic plc, for the use of their brand name.

    (4) Fixed overheads are estimated at £900,000 per annum. These overheads cannot be avoided until the end of the

    year in which the Snowballer is withdrawn from the market.

    (5) An initial investment of £5 million would be required. A government grant equal to 50% of the initial investment

    would be received on the date the investment is made. However, because the Snowballer would be classified as

    a luxury good, no tax allowances would be available on this initial investment. The estimated life cycle of the

    Snowballer is six years.

    (6) Corporation tax at the rate of 30% per annum is payable in the year in which profit occurs.

    (7) All cash flows are stated in current prices and, with the exception of the initial investment and the government

    grant, will occur at the end of each year.

    (8) The nominal cost of capital is 15·44%. Annual inflation during the period is expected to amount to 4%.

    Required:

    (a) Calculate the net present value (NPV) of the Snowballer proposal and recommend whether it should be

    undertaken by the directors of ITL. (4 marks)


    正确答案:

  • 第5题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第6题:

    “Cost of quality”is a project management concept that includes cost of( 73)

    A.exceedings requirements

    B.Changes to the requirements

    C.Ensuring conformance to requirements

    D.The quality control requirements


    正确答案:C

  • 第7题:

    In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)

    A.the quality of the schedule and cost control analysis

    B.customer satisfaction

    C.customer compromise in defining its needs

    D.exceeding customer requirements through gold-plating


    正确答案:B
    所有项目中,客户的要求必须根据进度表、成本和有限的资源进行修改。项目的成功主要取决于:A进度表和成本控制分析的优劣B.客户满意程度C客户在确定要求时的折衷态度D通过漂亮的外包装超额满足客户的要求所以答案选B。

  • 第8题:

    Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.

    A.Resource assignment matrix
    B.Change control plan
    C.Project charter
    D.Client organization chart

    答案:B
    解析:
    在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,变更控制计划文件提供了该信息。 A.资源分配矩阵 B.变更控制计划 C.项目章程 D.客户组织结构图

  • 第9题:

    A site administrator is configuring Resource-level access control.  Which of the following statements about Resource-level access control are true? Resource-level access control policies:()

    • A、are optional
    • B、are used to protect data beans
    • C、provide coarse-grained access control
    • D、never specify a relationship

    正确答案:A,B

  • 第10题:

    You are designing a top-level OU structure to meet the business and technical requirements.  Which top-evel OU or OUs should you use? ()

    • A、 ATC 
    • B、 Paris
    • C、 Berlin
    • D、 Sydney
    • E、 Manifast
    • F、 Human Resources

    正确答案:A,B

  • 第11题:

    单选题
    Which factor has the greatest impact on the estimated per unit labor cost for a project?()
    A

    Historical information

    B

    Use of outside vendors

    C

    Change control processes

    D

    Human resource skill level requirements


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
    A

    proceedings

    B

    controls

    C

    forecastings

    D

    Prelibations


    正确答案: C
    解析: 该题的关键词为"appropriate measures、 requirements volatility",其语句结构为"The project manager(主{吾) may, however, want to track(谓{吾) appropriate measures of requirements volatility(宾语) to judge whether new or revised()are necessary(目的状语从句)",含义为"项目经理也许会跟踪需求变化的相关度量,以判断是否应该调整的或者新的什么",因为整段文字讨论的内容都集中于需求变更管理,所以只分析最后一句即可,根据题意,应该在空白处填写"措施"一类的词汇,排除之后只有选项B比较适合,选项A、C和D都可以排除,尤其是选项D是一个很生僻的词汇,含义为"尝试"。

  • 第13题:

    144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A. Overhead rates, labor rates and material costs.

    B. Overhead rates, schedule slippages, and rework.

    C. Rework, cost-of-living adjustments, and overtime.

    D. Material costs, shipping cost, and scope changes.

    E. Labor rates, material costs, and cost reporting


    正确答案:A

  • 第14题:

    139 By which means is a contractor able to control cost overruns due to changing requirements? A. Project data review

    B. Change order

    C. Purchase order amendment

    D. Change control

    E. None of the above


    正确答案:D

  • 第15题:

    ● Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A Past project records (historical data)

    B Commercial techniques (standard practices, rules of thumb)

    C Past project team members knowledge (experience, oldtimers)

    D All of the above

    E A and C only


    正确答案:D

  • 第16题:

    The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B

  • 第17题:

    ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.

    (75) A. Resource assignment matrix

    B. Change control plan

    C. Project charter

    D. Client organization chart


    正确答案:B

  • 第18题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第19题:

    Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance. () is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

    A.Cost-Benefit
    B.Control charts
    C.Quality function deployment
    D.Cost of quality analysis

    答案:D
    解析:
    质量分析成本(Cost of quality analysis)是对产品或服务进行需求一致性分析所产生的成本;成本效益分析(Cost-Benefit analysis)是通过比较项目的全部成本和效益来评估项目价值的一种方法;控制图(Control charts )是项目质量控制方法;质量功能展开(Quality function deployment)是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法。因此选D。

  • 第20题:

    During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.

    • A、proceedings
    • B、controls
    • C、forecastings
    • D、Prelibations

    正确答案:B

  • 第21题:

    Which factor has the greatest impact on the estimated per unit labor cost for a project?()

    • A、Historical information
    • B、Use of outside vendors
    • C、Change control processes
    • D、Human resource skill level requirements

    正确答案:D

  • 第22题:

    You are designing a top-level OU structure to meet the business and technical requirements. Which top-evel OU or OUs should you use?()

    • A、ATC
    • B、Paris
    • C、Berlin
    • D、Sydney
    • E、Manifast
    • F、Human Resources

    正确答案:A,B

  • 第23题:

    单选题
    The most variable factor in the control of broken stowage is().
    A

    the use of excessive amounts of dunnage

    B

    the use of excessive amount of filler cargo

    C

    the failure to stow some item in neat and uniform rows and tiers

    D

    the skill, industry and interest of the longshoremen


    正确答案: B
    解析: 暂无解析

  • 第24题:

    多选题
    A site administrator is configuring Resource-level access control.  Which of the following statements about Resource-level access control are true? Resource-level access control policies:()
    A

    are optional

    B

    are used to protect data beans

    C

    provide coarse-grained access control

    D

    never specify a relationship


    正确答案: A,D