单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recomm

题目
单选题
Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()
A

Use the 60 Amp line cords

B

Change the 100 Amp connector to a 60 Amp circuit

C

Submit an RPQ to order the p5 590 with 100 Amp power cords

D

Change the configuration and order the p5 590 with the 100 Amp power cords


相似考题
更多“单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recomm”相关问题
  • 第1题:

    Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()

    • A、Upgrade the p690 to a p5 590 server running AIX 5.3
    • B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization
    • C、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters
    • D、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

    正确答案:D

  • 第2题:

    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()

    • A、VIO Server
    • B、AIX 5.2 ML4
    • C、Shared Ethernet Adapter
    • D、AIX 5.3 with Advanced Power Virtualization

    正确答案:D

  • 第3题:

    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()

    • A、Implement a proxy server to provide multiple sources to one destination 
    • B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 
    • C、Purchase a network hub or switch so both p5 570s can connect to the single HMC 
    • D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

    正确答案:C

  • 第4题:

    A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()

    • A、Have optional Fibre Channel and Ethernet switches been installed in the server?
    • B、What is the available kVA value of the UPS?
    • C、Are there sufficient empty socket outlets in the UPS?
    • D、What is the impact on the power consumption of the data center cooling system?

    正确答案:B

  • 第5题:

    Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()

    • A、Add CPU and memory COD so they have room to grow if required
    • B、Make the server configuration twice as large as the current requirement
    • C、Configure the server for the current capacity requirements
    • D、Make the server configuration a little larger than the current capacity requirements

    正确答案:A

  • 第6题:

    单选题
    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()
    A

    Implement a proxy server to provide multiple sources to one destination 

    B

    Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 

    C

    Purchase a network hub or switch so both p5 570s can connect to the single HMC 

    D

    Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()
    A

    The server must be installed into a location with a raised floor for optimum system cooling  and cable management.

    B

    The server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.

    C

    The server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.

    D

    The server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.


    正确答案: C
    解析: 暂无解析

  • 第8题:

    单选题
    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()
    A

    VIO Server

    B

    AIX 5.2 ML4

    C

    Shared Ethernet Adapter

    D

    AIX 5.3 with Advanced Power Virtualization


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()
    A

    A public internet connection

    B

    All of the Logical Partitions need to be active

    C

    One partition must be configured with Service Authority

    D

    A local Repository must be configured prior to the update


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()
    A

    Upgrade the p690 to a p5 590 server running AIX 5.3

    B

    Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization

    C

    Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters

    D

    Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    Companycom has just added some new disk drives to a p5 590. The customer needs to know the largest Logical Track Group that these drives will support. What is the best way to locate this information?()
    A

    Use lquerypv to read the drive

    B

    Use lspv and look at PP Size value

    C

    Look on the outside of the drive itself

    D

    Use bootinfo to find the LTG on the drive


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()
    A

    New install of AIX

    B

    Migrate the 7040-61D

    C

    Utilize alt_disk_install

    D

    Use the enterprise back up strategy


    正确答案: C
    解析: 暂无解析

  • 第13题:

    Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()

    • A、The server must be installed into a location with a raised floor for optimum system cooling  and cable management.
    • B、The server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.
    • C、The server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.
    • D、The server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.

    正确答案:A

  • 第14题:

    Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()

    • A、Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. 
    • B、Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. 
    • C、Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. 
    • D、Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.

    正确答案:C

  • 第15题:

    Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()

    • A、Use the 60 Amp line cords
    • B、Change the 100 Amp connector to a 60 Amp circuit
    • C、Submit an RPQ to order the p5 590 with 100 Amp power cords
    • D、Change the configuration and order the p5 590 with the 100 Amp power cords

    正确答案:D

  • 第16题:

    A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()

    • A、A public internet connection
    • B、All of the Logical Partitions need to be active
    • C、One partition must be configured with Service Authority
    • D、A local Repository must be configured prior to the update

    正确答案:C

  • 第17题:

    单选题
    Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()
    A

    Increase memory

    B

    Add more adapters

    C

    Increase both processors and adapters

    D

    Increase the number of processors by 20 - 30%


    正确答案: A
    解析: 暂无解析

  • 第18题:

    单选题
    Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()
    A

    Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. 

    B

    Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. 

    C

    Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. 

    D

    Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()
    A

    Use the 60 Amp line cords

    B

    Change the 100 Amp connector to a 60 Amp circuit

    C

    Submit an RPQ to order the p5 590 with 100 Amp power cords

    D

    Change the configuration and order the p5 590 with the 100 Amp power cords


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()
    A

    Add CPU and memory COD so they have room to grow if required

    B

    Make the server configuration twice as large as the current requirement

    C

    Configure the server for the current capacity requirements

    D

    Make the server configuration a little larger than the current capacity requirements


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    A customer wants to know what version of DirectX the current workstation has installed. Which of the following command line tools would the customer use?()
    A

    edit

    B

    systeminfo

    C

    gpedit.msc

    D

    dxdiag


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()
    A

    The p5 595 would allow for COD

    B

    The p5 595 includes the Advanced Power Virtualization hardware and software

    C

    The p5 595 is priced the same as the p5 590 given the same number/type of CPUs

    D

    The p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    When booting the p5 590 server in full system partition mode, which location is preferred for the fastest boot?()
    A

    A SAN device

    B

    First I/O drawer

    C

    Any I/O drawer within the main frame

    D

    First I/O drawer within the expansion frame


    正确答案: A
    解析: 暂无解析