niusouti.com

Your network consists of a single Active Directory domain.The domain contains more than 300 group objects. The group objects are divided between several regional organizational units (OUs).You need to create a list of all groups that have names that begin

题目

Your network consists of a single Active Directory domain.The domain contains more than 300 group objects. The group objects are divided between several regional organizational units (OUs).You need to create a list of all groups that have names that begin with the word Sales.Which command should you use? ()

A. Dsget group

B. Dsquery group

C. Netdom query

D. Net group


相似考题
更多“Your network consists of a single Active Directory domain.The domain contains more than 30 ”相关问题
  • 第1题:

    What's ( )job? Are ( ) British?

    A. your, your

    B. you, your

    C. your, you


    正确答案:C

  • 第2题:

    Refertotheexhibit.WhichofthefollowingIOSDHCPconfigurationstatementsisrequiredsothataCiscoskinny-basedIPphonecanconnectwithCallManager?()

    A.ipdhcppoolClient

    B.network10.1.1.0255.255.255.240

    C.default-router10.1.1.1

    D.dns-server10.2.2.2

    E.domain-namecisco.com

    F.option150ip10.3.3.3


    参考答案:F

  • 第3题:

    Which routing protocols will support the following IP addressing scheme? ()Network 1 - 192.168.10.0 /26Network 2 - 192.168.10.64 /27Network 3 - 192.168.10.96 /27Network 4 - 192.168.10.128 /30Network 5 - 192.168.10.132 /30

    A.RIP version 1

    B.RIP version 2

    C.IGRP

    D.EIGRP

    E.OSPF


    参考答案:B, D, E

  • 第4题:

    在HP 3PAR中,本地灾难恢复提供了什么功能?()

    A.file-based backup with metadata backup

    B.network-based backup

    C.point-in-time snapshot of an entire File Provisioning Group

    D.active/passive File Persona clusters on separate storage systems


    答案:C

  • 第5题:

    The Testking Network consists of the following 5 IP networks:NETWORK 1: 192.168.10.0/26NETWORK 2: 192.168.10.64/27NETWORK 3: 192.168.10.96/27NETWORK 4: 192.168.10.128/30NETWORK 5: 192.168.10.132/30Which of the following routing protocols will support this IP addressing scheme?()

    A. RIP version 1

    B. RIP version 2

    C. IGRP

    D. EIGRP

    E. OSPF

    F. BGP


    参考答案:B, D, E

  • 第6题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。