An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A.Total float for the activity

题目

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.

B.The early finish date ofthe activity is the end ofthe day on the 14th.

C.The late finish date is the 25th.

D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.


相似考题
更多“An activity has an early start date-of the lOth and a late start date of the 19th. The act ”相关问题
  • 第1题:

    假设已经配置好PATH环境变量,启动hadoop的命令是()。

    A.start-fs.sh

    B.start-hadoop.sh

    C.start-dfs.sh

    D.start-hdfs.sh


    start-dfs.sh

  • 第2题:

    结束Activity(活动)的方法是

    A.destory()

    B.start()

    C.finish()

    D.close()


    C

  • 第3题:

    1、启动hadoop所有进程的命令是:

    A.start-dfs.sh

    B.start-hadoop.sh

    C.start-all.sh

    D.start-hdfs.sh


    D

  • 第4题:

    假设已经配置好PATH环境变量,启动hadoop的命令是

    A.start-dfs.sh

    B.start-hadoop.sh

    C.start-fs.sh

    D.start-hdfs.sh


    start-dfs.sh

  • 第5题:

    13、假设已经配置好PATH环境变量,启动Hadoop的命令是:

    A.start-dfs.sh

    B.start-hadoop.sh

    C.start-fs.sh

    D.start-hdfs.sh


    JAVA_HOME = bin的上一层目录 path = %JAVA_HOME%\bin

  • 第6题:

    3、结束Activity(活动)的方法是

    A.destory()

    B.start()

    C.finish()

    D.close()


    finish