第1题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第2题:
( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.
A.Product scope description B.Project objectives C.Product specification D.The project scope statement
第3题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第4题:
In project time management processes,( )involves identifying and documenting the relationships between project activities.
A.activity definition
B.activity sequencing
C.schedule control
D.Schedule development
第5题:
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
第6题:
第7题:
第8题:
第9题:
第10题:
The inputs of developing project management plan do not include()
第11题:
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
第12题:
RationalClearcase
QualityFunctionDeployment
VisualSourceSafe
ConcurrentVersions System
第13题:
● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.
(74)
A.Rational Clearcase
B.Quality Function Deployment
C.Visual SourceSafe
D.Concurrent Versions System
第14题:
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
第15题:
Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.
A.communicating
B.collecting
C.filing
D.documenting
第16题:
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
第17题:
第18题:
第19题:
第20题:
第21题:
第22题:
( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.
第23题:
project scope statement
project requirement
project charter
product specification