( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate,and closing out contracts.A、Control ProcurementsB、Conduct ProcurementsC、plan Procurements managementD、Procurements

题目
( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate,and closing out contracts.

A、Control Procurements

B、Conduct Procurements

C、plan Procurements management

D、Procurements strategy


相似考题
更多“( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate,and closing out contracts. A、Control ProcurementsB、”相关问题
  • 第1题:

    The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    A.Plannlng

    B.Executing

    C.Monitoring and Controlling

    D.Closing


    正确答案:B
    解析:执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第2题:

    ● Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.(74) are the techniques and tools in performing quality control.

    Statistical sampling ① Run chart ②

    Control charts ③ Critical Path Method ④

    Pareto chart ⑤ Cause and effect diagrams ⑥

    (74)

    A.①②③④

    B.②③④⑤

    C.①②③⑤⑥

    D.①③④⑤⑥


    正确答案:C
    试题(74)分析
    实现项目质量控制的方法、技术和工具包括统计抽样Statistical sampling,运行图Run chart、控制图Control charts、帕累托图Pareto chart,以及因果图Cause and effect diagrams等。
    关键路径法Critical Path Method是制定项目进度计划的方法,因此选C
    参考答案
    (74)C

     

  • 第3题:

    Changes often happen in( ).

    A.Initiating Process

    B.Executing Process

    C.Planning Process

    D.Closing Process


    正确答案:B

  • 第4题:

    Schedule control is concerned with all the following except (74)

    A.influencing the factors that create schedule changes to ensure that the changes are beneficial

    B.determing that the schedule has changed

    C.managing the actual changes when and as they occur

    D.changing the shedule based on customer demands


    正确答案:D
    进度控制的内容:(1)确定项目进度的当前状态(2)对引起进度变更的因素施加影响,以保证这种变化朝着有利的方向发展(3)确定项目进度已经变更(4)当变更发生时管理实际的变更D选项“基本客于的需求改变进度”。依据PMBOK定义及上述内容,D选项不属于进度控制内容。

  • 第5题:

    Perform. Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes. ______ are the techniques and tools in performing quality control.. ① Statistical sampling ② Run chart ③ Control charts ④ Critical Path Method ⑤ Pareto chart ⑥ Cause and effect diagrams

    A.①②③④

    B.②③④⑤

    C.①②③⑤⑥

    D.①③⑤⑥


    正确答案:C

  • 第6题:

    Perform Quality Control is the process of monitoring and recording results*of executing the Quality Plan activities to assess performance and recommend necessary changes.() are the techniques and tools in performing quality control① Statistical sampling ② Run chart③ Control charts ④ Critical Path Method⑤ Pareto chart⑥ Cause and effect diagrams

    A.①②③④
    B.②③④⑤
    C.①②③⑤⑥
    D.①③④⑤⑥

    答案:C
    解析:
    实现项目质量控制的方法、技术和工具包括统计抽样(Statistical sampling)、运行图 (Run chart)、控制图(Control charts)、帕累托图(Pareto chart),以及因果图(Cause and effect diagrams)等。关键路径法(Critical Path Method)是制定项目进度计划的方法,因此选C。

  • 第7题:

    Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coordinating change implementation, monitoring and reporting on implementation, reviewing and closing ().


    A. change reason
    B. change model
    C. remediation plan
    D. change requests


    答案:D
    解析:

  • 第8题:

    ()is the process of managing procurement relationships,monitoring contract performance,and making?changes and corrections as appropriate,and closing out contracts.

    A.Control Procurements
    B.Conduct Procurements
    C.Plan Procurement management
    D.Procurement strategy

    答案:A
    解析:
    ()是管理采购关系、监控合同执行情况、进行适当的更改和更正以及结束合同的过程。
    A.控制采购B.实施采购C.计划采购管理D.采购策略

  • 第9题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第10题:

    Rate your level of proficiency with managing and maintaining a server environment, including monitoring system and server performance, managing Web servers, monitoring and analyzing events, managing software updates and site licenses, monitoring file and print servers, and managing servers remotely. ()

    • A、Very High
    • B、High
    • C、Moderate
    • D、Low
    • E、Very Low

    正确答案:A

  • 第11题:

    单选题
    After making changes to the monitoring configuration file for the event monitoring engine on an agent,  which conman command will force  the change immediately?()
    A

     loadconf

    B

     resetconf

    C

     deployconf

    D

     deploymonman


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    Rate your level of proficiency with managing and maintaining physical and logical devices, including managing basic and dynamic disks; monitoring server hardware; optimizing server disk performance; and installing, configuring, and troubleshooting server hardware devices. ()
    A

    Very High

    B

    High

    C

    Moderate

    D

    Low

    E

    Very Low


    正确答案: C
    解析: 暂无解析

  • 第13题:

    Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥


    正确答案:D
    执行质量控制是一个监督、评价项目质量计划活动执行结果和提出变更请求的过程。执行质量控制的技术和工具包括:活动网络图(Activity network diagram)、因果图(Cause and effect diagrams)、检查(Inspection)、流程图(Flow chart)和帕累托图(Pareto chart)等,但不包括工作分解结构(Work Breakdown Structure)。

  • 第14题:

    试题(74)

    Changes often happen in(74).

    (74)

    A.Initiating Process

    B.Executing Process

    C.Planning Process

    D.Closing Process


    正确答案:B
    试题(74)分析
    变更通常发生的阶段是。
    选项A是启动阶段,选项B是执行阶段,选项C是计划阶段,选项D是结项阶段。
    因此,正确答案是B。
    参考答案
    (74)B

  • 第15题:

    Configuration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of(75) identification.

    A.baseline

    B.value

    C.cost

    D.control


    正确答案:A
    解析:配置管理是在硬件、软件、固件、文件、测量等的过程管理的变化,作为变化需要有一个初始状态和下一个状态,标识上一状态变化非常重要,配置项目需确定重要状态的修订历史记录,主要目的是基线的确定。

  • 第16题:

    Schedule control is concerned with all the following except ( )

    A.influencing the factors that create schedule changes to ensure that the changes are beneficial

    B.determing that the schedule has changed

    C.managing the actual changes when and as they occur

    D.changing the shedule based on customer demands


    正确答案:D
    进度控制的内容:(1)确定项目进度的当前状态(2)对引起进度变更的因素施加影响,以保证这种变化朝着有利的方向发展(3)确定项目进度已经变更(4)当变更发生时管理实际的变更D选项“基本客于的需求改变进度”。依据PMBOK定义及上述内容,D选项不属于进度控制内容。

  • 第17题:

    In the last paragraph,the author mainly intends to

    A.list the necessary changes we ought to make

    B.advise US to make any necessary changes

    C.explain what changes can bring

    D. explain the process of making changes


    正确答案:B
    概括文章最后一段可知,作者建议我们,改变无所谓大小,只要必要就需要改变。A项是对文章的片面理解;C项是文章的细节,不是段落的主旨。

  • 第18题:

    ( )is not included in Perform Integrated Change Control Process.

    A.Defining subsidiary plans
    B.Approving changes
    C.Managing changes to deliverables
    D.Reviewing all change requests

    答案:A
    解析:
    执行变更控制过程中不包括定义附属计划。

  • 第19题:

    ( )is a process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

    A.Plan Cost Management
    B.Estimate Costs
    C.Determine Budget
    D.Control Costs

    答案:D
    解析:
    控制成本是一个监控项目状态的过程,目的是更新项目成本并且对成本基准的变化进行管理。

  • 第20题:

    The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    • A、Planning
    • B、Executing
    • C、Monitoring and Controlling
    • D、Closing

    正确答案:D

  • 第21题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Riskldentification
    • B、Quantitative RiskAnalysis
    • C、Qualitative RiskAnalysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第22题:

    After making changes to the monitoring configuration file for the event monitoring engine on an agent,  which conman command will force  the change immediately?()

    • A、 loadconf
    • B、 resetconf
    • C、 deployconf
    • D、 deploymonman

    正确答案:C

  • 第23题:

    单选题
    Rate your level of proficiency with managing and maintaining a server environment, including monitoring system and server performance, managing Web servers, monitoring and analyzing events, managing software updates and site licenses, monitoring file and print servers, and managing servers remotely. ()
    A

    Very High

    B

    High

    C

    Moderate

    D

    Low

    E

    Very Low


    正确答案: E
    解析: 暂无解析