A、Control Procurements
B、Conduct Procurements
C、plan Procurements management
D、Procurements strategy
第1题:
The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Plannlng
B.Executing
C.Monitoring and Controlling
D.Closing
第2题:
● Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.(74) are the techniques and tools in performing quality control.
Statistical sampling ① Run chart ②
Control charts ③ Critical Path Method ④
Pareto chart ⑤ Cause and effect diagrams ⑥
(74)
A.①②③④
B.②③④⑤
C.①②③⑤⑥
D.①③④⑤⑥
第3题:
Changes often happen in( ).
A.Initiating Process
B.Executing Process
C.Planning Process
D.Closing Process
第4题:
Schedule control is concerned with all the following except (74)
A.influencing the factors that create schedule changes to ensure that the changes are beneficial
B.determing that the schedule has changed
C.managing the actual changes when and as they occur
D.changing the shedule based on customer demands
第5题:
Perform. Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes. ______ are the techniques and tools in performing quality control.. ① Statistical sampling ② Run chart ③ Control charts ④ Critical Path Method ⑤ Pareto chart ⑥ Cause and effect diagrams
A.①②③④
B.②③④⑤
C.①②③⑤⑥
D.①③⑤⑥
第6题:
第7题:
第8题:
第9题:
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
第10题:
Rate your level of proficiency with managing and maintaining a server environment, including monitoring system and server performance, managing Web servers, monitoring and analyzing events, managing software updates and site licenses, monitoring file and print servers, and managing servers remotely. ()
第11题:
loadconf
resetconf
deployconf
deploymonman
第12题:
Very High
High
Moderate
Low
Very Low
第13题:
Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥
第14题:
试题(74)
Changes often happen in(74).
(74)
A.Initiating Process
B.Executing Process
C.Planning Process
D.Closing Process
第15题:
Configuration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of(75) identification.
A.baseline
B.value
C.cost
D.control
第16题:
Schedule control is concerned with all the following except ( )
A.influencing the factors that create schedule changes to ensure that the changes are beneficial
B.determing that the schedule has changed
C.managing the actual changes when and as they occur
D.changing the shedule based on customer demands
第17题:
In the last paragraph,the author mainly intends to
A.list the necessary changes we ought to make
B.advise US to make any necessary changes
C.explain what changes can bring
D. explain the process of making changes
第18题:
第19题:
第20题:
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
第21题:
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
第22题:
After making changes to the monitoring configuration file for the event monitoring engine on an agent, which conman command will force the change immediately?()
第23题:
Very High
High
Moderate
Low
Very Low