第1题:
A 4-way x445 server with 2GB of memory running Windows 2003 Server with Exchange 2003 is performing poorly. Users are complaining of slow response times when accessing their email. Which subsystem should be checked first as a potential bottleneck?()
第2题:
A customer is consolidating seven IBM i partitions onto a POWER7 system, using VIO Server to virtualize resources.Which of the following PowerVM editions is appropriate for this customer?()
第3题:
A customer needs a new database server. The database application has a high memory overhead but does not benefit from 8-way processing. They would like a rack mountable system, which will support four Xeon processors with 512KB of L2 cache and 16GB of main system memory. Which of the following will satisfy the customer’s requirements?()
第4题:
A customer is considering procuring HP servers with Virtual Server Environment (VSE) to consolidate servers and dynamically move resources between partitions. How can the technical sales representative position PowerVM as the solution to virtualize this server environment?()
第5题:
A customer’s current backup environment uses IBM Tivoli Storage Manager (TSM) over thecorporate LAN. A 500 GB Oracle database application was recently added to the SAN. Backupwindows are no longer being met. Which action should the storage specialist recommend?()
第6题:
All servers on your company’s network run Windows Server 2008 R2. The company is planning to virtualize a memory-intensive server application. You need to recommend CPUs for the virtualization host server. The CPUs must enable memory management enhancements in Microsoft Hyper-V Server 2008 R2. What are two possible CPU recommendations that will achieve this goal?()
第7题:
PowerVM supports shared servers compared to VSE
PowerVM supports shared processors and memory compared to VSE
PowerVM supports shared processors, memory and I/O compared to VSE
PowerVM supports DLPAR without a reboot and supports dedicated I/O compared to VSE
第8题:
x445 with four Xeon DP processors and 16GB of memory in a single SMP module
x445 with four Xeon MP processors and 16GB of memory in a single SMP module
x445 with two SMP modules each containing two Xeon DP processors and 8GB of memory
x445 with two SMP modules each containing two Xeon MP processors and 8GB of memory
第9题:
IBM i Edition
Express Edition
Standard Edition
Enterprise Edition
第10题:
networking
processor
memory
storage
第11题:
x445 with four Xeon MP processors and 8GB of memory
x445 with four Xeon MP processors and 16GB of memory in a single SMP module
x445 with four Xeon DP processors and 16GB of memory in a single SMP module
x445 with two SMP modules each containing two Xeon DP processors and 8GB of memory
第12题:
processor
storage
memory
networking
第13题:
A customer needs a new Microsoft Windows 2003 Server. They are running an application that requires substantial memory. They would like a rack mountable system, which will support four Xeon processors with 2MB of L3 cache. Which of the following is the minimum configuration to satisfy the customer’s requirements?()
第14题:
A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()
第15题:
Which are the two main uses of a VIO server?()
第16题:
A customer is looking for a reliable well-performing, cost-effective solution to a growing commercial workload. Initially, they want to run 12 UDB partitions, each of which would need two processors and 8GB of memory. They are looking at the p655 and want to start with three LPARS on each p655 node using a total of four nodes. Each LPAR would need at least 4 x 6239 fibre cards and 2 x 5706 2-port 10/100/1000 Ethernet cards. At a later date, they want to add an additional LPAR to each node to expand to a total of 16 UDB partitions. Which of the following major limitations of this solution should be mentioned to the customer?()
第17题:
You are designing a Hyper-V solution. You plan to virtualize an application server. The application server requires failover clustering that uses shared storage. You need to choose the correct storage solution. What should you choose?()
第18题:
two child partitions with VHDs stored on an iSCSI SAN
two child partitions with volumes mounted from an iSCSI SAN
two host servers with iSCSI-attached storage enabled for Cluster Shared Volumes (CSVs)
two host servers with Fibre ChannelCattached storage enabled for Cluster Shared Volumes (CSVs)
第19题:
A
B
C
D
第20题:
CPUs with AMD Virtualization (AMD V)
CPUs with AMD Rapid Virtualization Index (AMD RVI)
CPUs with Intel Extended Page Tables (Intel EPT)
CPUs with Intel Virtualization Technology (Intel VT)
第21题:
Virtualize network and memory to LPARs.
Virtualize network and storage to LPARs.
Virtualize memory and processors to LPARs.
Virtualize storage and processors to LPARs.
第22题:
PowerVM offers partition mobility.
PowerVM can virtualize network and SAN resources.
PowerVM supports multiple operating systems running concurrently.
PowerVM allows an LPAR to use activated cores and memory without limitation.
第23题:
Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.
Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.
Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.
第24题:
Windows Virtual PC
Remote Desktop Services (RDS)
Microsoft Application Virtualization (App-V)