Software system test plan needs to be compiled in( )phase。 软件系统测试计划需要在( )阶段编制。A.requirement analysis 需求分析B.Outline design 概要设计C.detailed design 详细设计D.Coding phase 编码阶段

题目
Software system test plan needs to be compiled in( )phase。
软件系统测试计划需要在( )阶段编制。

A.requirement analysis
需求分析
B.Outline design
概要设计
C.detailed design
详细设计
D.Coding phase
编码阶段

相似考题
更多“Software system test plan needs to be compiled in( )phase。 ”相关问题
  • 第1题:

    Black-box and white-box testing method ale often used in software testing phase, in which, the white-box is mainly used to test software's(73).

    A.external function of a program

    B.reasonableness of structure

    C.internal logic of a program

    D.correctness of a program


    正确答案:C
    解析:本题考查专业英语应用能力和软件测试方法。软件测试的目的就是在软件系统交付运行之前,尽可能多地发现系统中的错误和缺陷。常用的软件测试方法有黑盒测试与白盒测试方法。其中黑盒测试又称功能测试,它把软件看做一个不透明的黑盒子,完全不考虑(或不了解)软件的内部结构和处理算法,它只检查软件功能是否能按照软件需求说明书的要求正常使用,软件是否能适当地接收输入数据并产生正确的输出信息,软件运行过程中能否保持外部信息(例如文件和数据库)的完整性等。而白盒测试又称结构测试,它的前提是可以把程序看成装在一个透明的白盒子里,测试者完全知道程序的结构和处理算法。这种方法按照程序内部逻辑设计测试用例,检测程序中的主要执行通路是否都能按预定要求正确工作。参考译文:黑盒测试与白盒测试方法是常被使用的软件测试方法,其中自盒测试主要用来测试软件的程序内部逻辑结构。

  • 第2题:

    The purpose of the requirements definition phase is to produce a clear,complete,consistent,and testable( )of the technical requirements for the software product.During the requirements definition phase,the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the software must perform and each(请作答此空)that it must meet.The starting point is usually a set of high level requirements from the( )that describe the project or problem.In either case,the requirements definition team formulates an overall concept for the system and then defines( )showing how the system will be operated publishes the system and operations concept document and conducts a system concept review(SCR).Following the SCR,the team derives( )requirements for the system from the high level requirements and the system and operations concept.using structured or object-oriented analysis.the team specifies the software functions and algorithms needed to satisfy each detailed requirement.

    A.criterion
    B.standard
    C.model
    D.system

    答案:A
    解析:

  • 第3题:

    A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements evolve from broad statements of overall ( 71)from the system to detailed statements of the business capabilities that a system should support to detailed technical statements of the way in which the capabilities will be implemented in the new system. (72)focus on describing how to create the software product that will be produced from the project Nonfunctional requirements are primarily used in the design phase when decisions are made about the user interface, the hardware and software, and the system's underlying architecture. The system's physical and technical environments would be considered (73). The speed, capacity, and reliability of the system belong to (74).(75)describes that who has authorized access to the system under what circumstances.
    (72)处应选?

    A.User requirements
    B.Business requirements
    C.Function requirements
    D.System requirements

    答案:C
    解析:
    需求只是陈述了系统必须做什么或者系统需要有什么特性,需求来自于从系统总体(71)的广泛陈述到系统所支持业务能力的详细陈述,再到新系统能力实现中所采用方法的详细技术陈述。(72)致力于描述如何创建将在项目中产生的软件产品。非功能性需求主要在设计阶段中做出关于用户界面、硬件和软件,以及系统底层架构的决策时使用。系统的物理和技术环境将被看作一种(73)。系统的速度、能力和可靠性属于(74)。(75)描述了谁在什么情况下具有访问系统的权限。

    (72) A.用户需求 B.业务需求

    C.功能需求 D.系统需求

  • 第4题:

    A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements evolve from broad statements of overall (71)from the system to detailed statements of the business capabilities that a system should support to detailed technical statements of the way in which the capabilities will be implemented in the new system. ( )focus on describing how to create the software product that will be produced from the project Nonfunctional requirements are primarily used in the design phase when decisions are made about the user interface, the hardware and software, and the system's underlying architecture. The system's physical and technical environments would be considered ( ). The speed, capacity, and reliability of the system belong to ( ).( )describes that who has authorized access to the system under what circumstances.

    (71)应选?

    A.business needs
    B.operation processes
    C.technical specification
    D.function components

    答案:A
    解析:
    需求只是陈述了系统必须做什么或者系统需要有什么特性,需求来自于从系统总体(71)的广泛陈述到系统所支持业务能力的详细陈述,再到新系统能力实现中所采用方法的详细技术陈述。(72)致力于描述如何创建将在项目中产生的软件产品。非功能性需求主要在设计阶段中做出关于用户界面、硬件和软件,以及系统底层架构的决策时使用。系统的物理和技术环境将被看作一种(73)。系统的速度、能力和可靠性属于(74)。(75)描述了谁在什么情况下具有访问系统的权限。

    (71) A.业务需求 B.操作流程

    C.技术规范 D.功能组件

  • 第5题:

    The deliverable from this phase also includes the ( ) for the proposed system.

    A.hardware and software specification
    B.system performance specification
    C.formal requirements definition
    D.general problem statement

    答案:C
    解析:
    除了提交现行系统的过程和数据的逻辑模型外,这一分析阶段的交付物还包括推荐系统的正式需求定义。
    A.软硬件规格 B.系统性能规范 C.正式需求定义 D.通用问题说明

  • 第6题:

    Which design phase service component includes the development and documentation of the test case or cases used to verify that a deployed infrastructure meets operational, functional, and interface requirements? Select exactly 1 answer(s) from the following:()。

    • A、Implementation Plan
    • B、Business Plan
    • C、Staging Plan
    • D、Detailed Design Development
    • E、Systems Acceptance Test Plan Development

    正确答案:E

  • 第7题:

    Which three of these service components are in the design phase?()

    • A、Account Qualification and Planning
    • B、Detailed Design Development
    • C、Staff Training
    • D、Systems Acceptance Test Plan Development
    • E、Staging Plan Development
    • F、Site Readiness Assessment

    正确答案:B,D,E

  • 第8题:

    Which service component in the design phase describes developing a detailed, site-specific plan for implementing the new technology system or solution()

    • A、Implementation Plan Development
    • B、Detailed Design Development
    • C、Systems Acceptance Test Plan Development
    • D、Staging Plan Development

    正确答案:A

  • 第9题:

    A manufacturer has instructed a technician to update the software that resides on the flash ROMchip of an integral system add-in component. Which of the following types of software needs to be updated?()

    • A、System BIOS
    • B、Firmware
    • C、OS Patch
    • D、Driver

    正确答案:B

  • 第10题:

    单选题
    In which phase is a systems acceptance test plan developed and documented?()
    A

    Implement

    B

    Design

    C

    Prepare

    D

    Operate


    正确答案: A
    解析: 暂无解析

  • 第11题:

    多选题
    Which three of these service components are in the design phase?()
    A

    Account Qualification and Planning

    B

    Detailed Design Development

    C

    Staff Training

    D

    Systems Acceptance Test Plan Development

    E

    Staging Plan Development

    F

    Site Readiness Assessment


    正确答案: C,F
    解析: 暂无解析

  • 第12题:

    单选题
    Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()
    A

    staging and system migration

    B

    post implementation support handoff meeting

    C

    detailed design development

    D

    staff training

    E

    migration plan development


    正确答案: A
    解析: 暂无解析

  • 第13题:

    In which phase is a systems acceptance test plan developed and documented? ()

    A.Implement

    B.Design

    C.Prepare

    D.Operate


    参考答案:B

  • 第14题:

    The purpose of the requirements definition phase is to produce a clear,complete,consistent,and testable( )of the technical requirements for the software product.During the requirements definition phase,the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the software must perform and each( )that it must meet.The starting point is usually a set of high level requirements from the(请作答此空)that describe the project or problem.In either case,the requirements definition team formulates an overall concept for the system and then defines( )showing how the system will be operated publishes the system and operations concept document and conducts a system concept review(SCR).Following the SCR,the team derives( )requirements for the system from the high level requirements and the system and operations concept.using structured or object-oriented analysis.the team specifies the software functions and algorithms needed to satisfy each detailed requirement.

    A.producer
    B.customer
    C.programmer
    D.analyser

    答案:B
    解析:

  • 第15题:

    A requirement is simply a statement of what the system must do or what characteristics it needs to have. Requirements evolve from broad statements of overall (71)from the system to detailed statements of the business capabilities that a system should support to detailed technical statements of the way in which the capabilities will be implemented in the new system. (72)focus on describing how to create the software product that will be produced from the project Nonfunctional requirements are primarily used in the design phase when decisions are made about the user interface, the hardware and software, and the system's underlying architecture. The system's physical and technical environments would be considered (73). The speed, capacity, and reliability of the system belong to (74).(75)describes that who has authorized access to the system under what circumstances.

    (74)应选?

    A.security requirement
    B.performance requirement
    C.technical requirement
    D.information requirement

    答案:B
    解析:
    需求只是陈述了系统必须做什么或者系统需要有什么特性,需求来自于从系统总体(71)的广泛陈述到系统所支持业务能力的详细陈述,再到新系统能力实现中所采用方法的详细技术陈述。(72)致力于描述如何创建将在项目中产生的软件产品。非功能性需求主要在设计阶段中做出关于用户界面、硬件和软件,以及系统底层架构的决策时使用。系统的物理和技术环境将被看作一种(73)。系统的速度、能力和可靠性属于(74)。(75)描述了谁在什么情况下具有访问系统的权限。

    (74) A.安全性需求 B.性能性需求

    C.技术性需求 D.非功能性需求

  • 第16题:

    In software engineering the design phase is divided into ( ).

    A.system design and detailed design
    B.computer design and program design
    C.system design and hardware design
    D.computer design and detailed design

    答案:A
    解析:
    翻译:

    在软件工程中设计阶段可以分为( )。

    A. 系统设计与详细设计 B. 计算机设计与程序设计

    C. 系统设计与硬件设计 D. 计算机设计与详细设计

  • 第17题:

    Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()

    • A、staging and system migration
    • B、post implementation support handoff meeting
    • C、detailed design development
    • D、staff training
    • E、migration plan development

    正确答案:A

  • 第18题:

    Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。

    • A、Detailed Design Development
    • B、Systems Acceptance Test Plan Development
    • C、Staging Plan
    • D、Implementation Plan Development
    • E、Project Kick-off

    正确答案:D

  • 第19题:

    In the operate phase, providing and maintaining reliable, current information about the wlan system hardware, software,and applications pertinent to the system’s individual components and attributes is part of which service component?()

    • A、problem management
    • B、configuration management
    • C、incident management
    • D、change management

    正确答案:B

  • 第20题:

    Which service component in the wireless operate phase helps isolate and resolve an incident?()

    • A、change management
    • B、configuration management
    • C、incident management
    • D、acceptance test plan

    正确答案:C

  • 第21题:

    单选题
    A manufacturer has instructed a technician to update the software that resides on the flash ROMchip of an integral system add-in component. Which of the following types of software needs to be updated?()
    A

    System BIOS

    B

    Firmware

    C

    OS Patch

    D

    Driver


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    What is the primary objective of the plan phase()
    A

    Assess the existing environments to determine if it can support the proposed system.

    B

    Identify the activities for installing and configuring the equipment at the customer sites.

    C

    Gather high-level solution requirements, and understand the customer business needs an the opportunity.

    D

    Prepare the activities for day-to-day support, management, and monitoring of the newly implemented system.


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    What is one key objective of the operations readiness assessment performed in the plan phase?Select exactly 1 answer(s) from the following:()。
    A

    align business requirements with technical requirements

    B

    create a plan to recycle used equipment

    C

    evaluate the readiness of a customers current operations and network management infrastructure to support a new technology

    D

    install and test system components in a non-production environment


    正确答案: A
    解析: 暂无解析