Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A.IntegrationB.TimeC.PlanningD.Commu

题目

Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

A.Integration

B.Time

C.Planning

D.Communication


相似考题
更多“Project(74)Management is the Knowledge Area that employs the processes required to ensure ”相关问题
  • 第1题:

    ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    A.Integration

    B.Scope

    C.Configuration

    D.Requiremen


    正确答案:B

  • 第2题:

    ● The inputs of developing project management plan do not include (72).

    (72)

    A. project charter

    B. stakeholder management strategy

    C. project scope statement

    D. outputs from planning processes


    正确答案:B

  • 第3题:

    The inputs of developing project management plan do not include (72) .

    A.project charter

    B.stakeholder management strategy

    C.project scope statement

    D.outputs from planning processes


    正确答案:B

  • 第4题:

    Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication


    正确答案:D
    项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

  • 第5题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第6题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第7题:

    The inputs of developing project management plan do not include()

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括:A.项目章程 B.利益相关者管理策略 C.项目范围描述 D.计划过程输出

  • 第8题:

    The inputs of developing project management plan do not include ().

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括 () 。
    A.项目章程 B.干系人管理策略
    C.项目范围说明书 D.计划过程输出

  • 第9题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第10题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D

  • 第11题:

    单选题
    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
    A

    Project

    B

    project management team

    C

    performingorganization

    D

    customer


    正确答案: B
    解析: 该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第12题:

    单选题
    The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
    A

    Planning

    B

    Executing

    C

    Monitoring and Controlling

    D

    Closing


    正确答案: D
    解析: 该题的关键词为"accomplish the project's requirements",其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",含义为"用于完成工作的过程组成什么过程组",所以可知重点描述为"完成工作",根据项目管理五个过程组的特点,选择Executing(执行)过程组,其他选项容易排除。

  • 第13题:

    ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

    (74) A. Product scope description

    B. Project objectives

    C. Product specification

    D. The project scope statement


    正确答案:D

  • 第14题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第15题:

    The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


    正确答案:B
    制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

  • 第16题:

    Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

    A.Developing project charter

    B.Developing project management plan

    C.Analyzing project risks

    D.Monitoring and controlling project


    正确答案:C

  • 第17题:

    Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围管理包括为确保项目包含且仅包含成功完成项目必需工作的所需过程。

  • 第18题:

    Project(29)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

    A.Integration

    B.Time

    C.Planning

    D.Communication


    正确答案:D
    解析:项目沟通管理是使用所需过程,以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

  • 第19题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第20题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第21题:

    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:B

  • 第22题:

    单选题
    Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.
    A

    Integration

    B

    Time

    C

    Planning

    D

    Communication


    正确答案: D
    解析: 该题的关键词较多,不过都是并列的关系,包括"ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition、 projectinformation"。其主要语句结构为"Project()Management(主语)is(谓语)the Knowledge Area",含义为"项目什么管理是知识领域",后续的定语从句说明该知识领域的特点。其实根据关键词"Proj ect information"考生可以很容易识别出来应该是项目沟通管理。

  • 第23题:

    单选题
    Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
    A

    Integration

    B

    Time

    C

    Planning

    D

    Communication


    正确答案: A
    解析: 暂无解析

  • 第24题:

    单选题
    The inputs of developing project management plan do not include()
    A

    project charter

    B

    stakeholder management strategy

    C

    project scope statement

    D

    outputs from planning processes


    正确答案: B
    解析: 中文解释:制定项目管理计划的输入不包括 A.项目章程 B.干系人管理策略 C.项目范围说明书 D.计划过程输出