Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
第1题:
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
t
A.Integration
B.Scope
C.Configuration
D.Requiremen
第2题:
● The inputs of developing project management plan do not include (72).
(72)
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
第3题:
The inputs of developing project management plan do not include (72) .
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
第4题:
Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication
第5题:
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A.performing organization
B.project management team
C.project
D.customer
第6题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第7题:
第8题:
第9题:
The inputs of developing project management plan do not include()
第10题:
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
第11题:
Project
project management team
performingorganization
customer
第12题:
Planning
Executing
Monitoring and Controlling
Closing
第13题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第14题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第15题:
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第16题:
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
第17题:
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
第18题:
Project(29)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
第19题:
第20题:
第21题:
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
第22题:
Integration
Time
Planning
Communication
第23题:
Integration
Time
Planning
Communication
第24题:
project charter
stakeholder management strategy
project scope statement
outputs from planning processes