22 The three most common types of project cost estimates are:
A. Order of magnitude, parametric, and budget.
B. Parametric, definitive and top down.
C. Order of magnitude, definitive and bottom up.
D. Order of magnitude, budget and definitive.
E. Analogy, parametric and top down
第1题:
A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A . Parametric
B . Definitive.
C . Budget
D . Bottom up.
E . Top down.
第2题:
The three most common types of project cost estimates are:
A . Order of magnitude, parametric, and budget.
B . Parametric, definitive and top down.
C . Order of magnitude, definitive and bottom up.
D . Order of magnitude, budget and definitive.
E . Analogy, parametric and top down.
第3题:
168 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A. Definitive, bottom up.
B. Analogy, top down.
C. Parametric, bottom up.
D. Parametric, top down.
E. Analogy, bottom up
第4题:
110 What is the purpose of the Project Plan?
A. To document the Preliminary estimates.
B. To document the Definitive estimates.
C. To document the Budgetary estimates.
D. To document Parametric estimates.
E. To document Order of Magnitude estimates
第5题:
166 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above
第6题:
59 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A. Parametric
B. Definitive.
C. Budget
D. Bottom up.
E. Top down
第7题:
65 Parametric estimates are based on variables such as:
A. Detailed planning and cost restraints.
B. Physical characteristics and historical data.
C. The WBS and similar projects.
D. Project objectives and manpower allocations.
E. Precise measurements and multiple inputs
第8题:
● What is the purpose of the Project Plan?
A To document the Preliminary estimates.
B To document the Definitive estimates.
C To document the Budgetary estimates.
D To document Parametric estimates.
E To document Order of Magnitude estimates.
第9题:
The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.
A.reserve analysis
B.cost aggregation
C.parametric estimating
D.funding limit reconciliation
第10题:
第11题:
震级(magnitude)
第12题:
1.5 and greater
1.25 and greater
1.0 and greater
0.5 and greater
第13题:
Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A . Definitive, bottom up.
B . Analogy, top down.
C . Parametric, bottom up.
D . Parametric, top down.
E . Analogy, bottom up.
第14题:
140 The three most common types of project cost estimates are:
A. Order of magnitude, parametric, and budget.
B. Parametric, definitive and top down.
C. Order of magnitude, definitive and bottom up.
D. Order of magnitude, budget and definitive.
E. Analogy, parametric and top down
第15题:
177 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A. Parametric
B. Definitive.
C. Budget
D. Bottom up. E
. Top down
第16题:
84 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above.
第17题:
50 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A. Definitive, bottom up.
B. Analogy, top down.
C. Parametric, bottom up.
D. Parametric, top down.
E. Analogy, bottom up.
第18题:
19 Parametric cost estimating involves
A. using the WBS to do bottom up estimates
B. defining the perimeters of the life-cycle
C. calculating the individual estimates of work packages
D. using a statistical model to estimate costs
E. A and C
第19题:
三个最常用的项目成本估算模式是( )
A.数学模拟order of magnitude参数法parametric及预算budget
B.参数法parametric确定的definitive及自上而下法top down
C.数学模拟order of magnitude确定的definitive及自下而上法bottom up
D.数学模拟order of magnitude预算budget及确定性的definitive
第20题:
The(7)technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A.cost aggregation
B.reserve analysis
C.parametric estimating
D.funding limit reconciliation
第21题:
第22题:
第23题:
2.5 times as bright as a second magnitude star
3 times as bright as a second magnitude star
5 times as bright as a second magnitude star
10 times as bright as a second magnitude star