正确答案:E
更多“Cost management includes processes that are required to maintain financial control of projects. These processes may include:A . economic evaluationB . cost estimatingC . cost forecastingD . B and CE . All of the above.”相关问题
  • 第1题:

    A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.

    A . Inventory control.

    B . Materials management.

    C . Procurement.

    D . All of the above.

    E . A and C only.


    正确答案:B

  • 第2题:

    Range estimating in determining cost risk probabilities requires _____ .

    A an amount of financial exposure.

    B risks and opportunities ranked in order of bottom line importance

    C contingency requirements for expected level of confidence

    D probability of cost overrun occurrences

    E All of the above.


    正确答案:E

  • 第3题:

    Which of the following types of contracts is equivalent to a cost plus contract:

    A Fixed firm price

    B Cost reimbursable

    C Fixed price plus incentive fee

    D progress payments

    E All of the above.


    正确答案:B

  • 第4题:

    84 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above.


    正确答案:B

  • 第5题:

    166 In which of the following cost estimating techniques are statistics models used:

    A. nonparametric cost estimating

    B. parametric cost estimating

    C. life cycle cost estimating

    D. bottom-up estimating

    E. All of the above


    正确答案:B

  • 第6题:

    ● Which of the following are types of status reports?

    A document, variance, trend and exception

    B cost, trend, schedule and acquisition

    C cost, schedule, technical performance

    D analysis, cost, performance and schedule

    E All of the above.


    正确答案:C

  • 第7题:

    ● Scope management is:

    A a project control function.

    B employs change control.

    C a work authorization process.

    D considers Cost, Quality and Schedule.

    E All of the above.


    正确答案:E

  • 第8题:

    “Cost of quality”is a project management concept that includes cost of( 73)

    A.exceedings requirements

    B.Changes to the requirements

    C.Ensuring conformance to requirements

    D.The quality control requirements


    正确答案:C

  • 第9题:

    Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围里管理包括为确保项目包含且仅只包含成功完成项目必需工作的所需过程。

  • 第10题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第11题:

    ()is the application of planned,systematic.quality activities to ensure that the project will employ all processes to meet requirements.

    A.Quality assurance
    B.Quality planning
    C.Quality control
    D.Quality cost

    答案:A
    解析:
    翻译:
    ()是计划的应用于系统的质量活动,确保该项目将采用所有流程来满足需求。
    A.质量保证B..质量计划C.质量控制D..质量成本

  • 第12题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D

  • 第13题:

    Cost management includes:

    A . Cost estimating/forecasting.

    B . Cost budgeting/cost control.

    C . Cost applications.

    D . All of the above.

    E . A and B only.


    正确答案:D

  • 第14题:

    In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

    A unit price

    B cost plus incentive fee

    C cost plus fixed fee

    D firm fixed price

    E B and D only


    正确答案:D

  • 第15题:

    98 Cost management includes:

    A. Cost estimating/forecasting.

    B. Cost budgeting/cost control.

    C. Cost applications.

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第16题:

    127 Cost management includes processes that are required to maintain financial control of projects. These processes may include:

    A. economic evaluation

    B. cost estimating

    C. cost forecasting

    D. B and C

    E. All of the above


    正确答案:E

  • 第17题:

    57 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above.


    正确答案:C

  • 第18题:

    ● Selection criteria for project selection include:

    A cost versus benefit

    B risk

    C contribution towards organizational goals

    D rate of return

    E All of the above.


    正确答案:E

  • 第19题:

    ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    A.Integration

    B.Scope

    C.Configuration

    D.Requiremen


    正确答案:B

  • 第20题:

    Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

    A.Integration

    B.Configuration

    C.Scope

    D.Requirement


    正确答案:C

  • 第21题:

    Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.

    A.cost management
    B.change management
    C.configuration management
    D.capacity management

    答案:B
    解析:

  • 第22题:

    Much of the effort cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures . The key to effective cost control is the management of the approved ( ) .

    A.Schedule baseline
    B.Cost baseline
    C.Cost output
    D.Cost input

    答案:B
    解析:
    解析:翻译:成本控制的大部分工作涉及分析项目资金消耗与这些支出所完成工作之间的关系。有效成本控制的关键是管理批准的( )。A.进度基准B.成本基准C.成本输出D.成本输入

  • 第23题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C