Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:
A.The project's schedule will be reduced by weeks.
B.The available slack on the noncritical paths will increase.
C.A new critical path may appear after the crash.
D.All of the above.
E.A and B only.