15 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events
第1题:
Risk event probability is defined as:
A the total number of possible events divided into the expectations or frequency of the risk event
B the number of times the risk event may occur
C the fraction of the total project tasks which may be affected by the risk event
D the total number of possible events divided into the consequences of the risk event.
E A and B
第2题:
Total Project Risk:
A should not be calculated for small projects
B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D A and B
E A and C
第3题:
Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
第4题:
23 Which of the following actions is an example of risk response:
A. adjust project parameters (scope, time, quality ...)
B. reduce the probability of potential project risk events C. reduce the consequences of potential project risk events
D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E. A, B and C only
第5题:
85 The purpose of project Risk Management is to:
A. Identify those factors that will adversely impact project objectives.
B. Assess the impact of adverse project factors.
C. Assess the probability of adverse project factors.
D. A and C
E. All of the above
第6题:
122 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第7题:
144 Risk event probability is defined as:
A. the total number of possible events divided into the expectations or frequency of the risk event
B. the number of times the risk event may occur
C. the fraction of the total project tasks which may be affected by the risk event
D. the total number of possible events divided into the consequences of the risk event.
E. A and B
第8题:
11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A. Reduce features and/or functionality
B Increase risk.
C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D. All of the above.
E. A and B only
第9题:
In Project Risk Management, Risk Response may include actions to:
A. reduce the probability of risk events
B. change the scope, budget, schedule or quality specifications of the project
C. reduce the consequences or severity of impacts of a potential risk event
D. A and C
E. All of the above
第10题:
105 Which of the following actions is an example of risk response:
A. adjust project parameters (scope, time, quality ...)
B. reduce the probability of potential project risk events
C. reduce the consequences of potential project risk events
D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E. A, B and C only
第11题:
Since risk is associated with most projects,the best course of action is to ( )
A.cover all project risks by buying appropriate insurance
B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner
C.avoid project with clear and present risk
D.identify various risks and implement actions to mitigate their potential impact
第12题:
The total current flow equals the sum of the individual currents
The total current flow equals the reciprocal of the sum of the individual currents
The total resistance equals the sum of the individual resistance
The total voltage equals the sum of the individual voltages across each resistance
第13题:
In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
第14题:
By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
第15题:
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
第16题:
59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A. Significantly reduce project risks
B. eliminate project risks
C. provide a rational basis for better decision making
D. identify risks, their impact(s), and any appropriate responses
E. None of the above
第17题:
108 Project Risk Management is based on which of the following premises:
A. the future is unknown.
B. unknowns can result in risks or opportunities.
C. we cannot control risk events.
D. project risk impact can be measured and controlled
E. All of the above
第18题:
125 In Project Risk Management, Risk Response may include actions to:
A. reduce the probability of risk events
B. change the scope, budget, schedule or quality specifications of the project
C. reduce the consequences or severity of impacts of a potential risk event
D. A and C
E. All of the above
第19题:
187 Budgeted contingencies can be detemined by:
A. past experience
B. applying standard allowances
C. detemining the sum total of the most probable variances of the various risk items properly identified. D. All of the above.
E. None of the above
第20题:
170 Project Risk _____ .
A. should not be calculated for small projects.
B. is the probability of each risk event minus the sum of the consequences of potential risk events.
C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D. cannot be quantified for first time projects.
E. B or D
第21题:
97 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events
第22题:
Since risk is associated with most projects,the best course of action is to (71)
A.cover all project risks by buying appropriate insurance
B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner
C.avoid project with clear and present risk
D.identify various risks and implement actions to mitigate their potential impact
第23题: