20 Most quality problems:A. originate in the quality department where the ultimate responsibility for quality rests.B. originate on the shop floor because of waste and product rework.C. are the results of management inattention to potential quality improv

题目

20 Most quality problems:

A. originate in the quality department where the ultimate responsibility for quality rests.

B. originate on the shop floor because of waste and product rework.

C. are the results of management inattention to potential quality improvement ideas.

D. could be eliminated if shop supervisors monitored their work more closely.

E. A and B


相似考题
更多“20 Most quality problems:A. originate in the quality department where the ultimate responsibility for quality rests.B. originate on the shop floor because of waste and product rework.C. are the results of management inattention to potential quality improv”相关问题
  • 第1题:

    The use of quality circles:

    A . has proven ineffective in both Japan and the U.S.

    B . is particularly effective in overcoming labor/management conflicts.

    C . provides a quick fix for most quality problems.

    D . allows workers the opportunity to generate solutions for chronic quality problems.

    E . A and B only


    正确答案:D

  • 第2题:

    Which of the following statements about the cost of quality are true?

    A . the cost of quality is the expense of nonconformance to requirements and specifications.

    B . the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.

    C . quality control programs should be implemented when the cost of quality are deemed affordable by management.

    D . A and B.

    E . A and C


    正确答案:A

  • 第3题:

    16 Which of the following statements about the cost of quality are true?

    A. the cost of quality is the expense of nonconformance to requirements and specifications.

    B. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product. C. quality control programs should be implemented when the cost of quality are deemed affordable by management.

    D. A and B.

    E. A and C


    正确答案:A

  • 第4题:

    69 The use of quality circles:

    A. has proven ineffective in both Japan and the U.S.

    B. is particularly effective in overcoming labor/management conflicts.

    C. provides a quick fix for most quality problems.

    D. allows workers the opportunity to generate solutions for chronic quality problems.

    E. A and B only


    正确答案:D

  • 第5题:

    3 In order to achieve long-term quality improvements, management must do the following:

    A. Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.

    B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.

    C. Implement of a formal quality control program with worker and management involvement.

    D. Establish financial incentive packages for worker.

    E. A and D


    正确答案:C

  • 第6题:

    98 Which of the following statements about the cost of quality are true?

    A. the cost of quality is the expense of nonconformance to requirements and specifications.

    B. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.

    C. quality control programs should be implemented when the cost of quality are deemed affordable by management.

    D. A and B.

    E. A and C


    正确答案:A

  • 第7题:

    ● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C

  • 第8题:

    Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


    正确答案:C

    项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第9题:

    Quality management ensures that an organization,product or service is (1).It has four main components:quality planning,quality assurance,quality control and quality (2).

    A.guaranteed

    B.sustain

    C.good

    D.consistent@@@SXB@@@A.improvement

    B.change

    C.spiral

    D.evolution


    正确答案:D,A

  • 第10题:

    下列组合正确的是A.质量管理——quality controlB.质量管理——quality management

    下列组合正确的是

    A.质量管理——quality control

    B.质量管理——quality management

    C.质量管理——quality assumnce

    D.质量管理——quality circle

    E.质量管理——total quality management


    正确答案:B
    质量管理——qualitymanage—ment,就是制定质量计划,并为实现该计划所开展的一切活动的总和。

  • 第11题:

    ( )The process of translating the quality management plan into eecutable quality activities that incorporate the organization's quality policies into the project.

    A:Munage quality
    B:Quality audit
    C:Quality metrics
    D:Quality improvement

    答案:C
    解析:

  • 第12题:

    Customers return the product because of()

    • A、Quantity  
    • B、Quality  
    • C、Quality control  
    • D、Quality unqualified

    正确答案:D

  • 第13题:

    Most quality problems:

    A . originate in the quality department where the ultimate responsibility for quality rests.

    B . originate on the shop floor because of waste and product rework.

    C . are the results of management inattention to potential quality improvement ideas.

    D . could be eliminated if shop supervisors monitored their work more closely.

    E . A and B


    正确答案:C

  • 第14题:

    ● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

    (74)

    A. quality planning

    B. quality assurance

    C. quality performance

    D. quality control


    正确答案:D

  • 第15题:

    41 In the project environment, the individual ultimately responsible for quality control is:

    A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D. The project manager who has ultimate responsibility for the entire project.

    E.the customer who must ensure that he is receiving a quality product from the vendor


    正确答案:D

  • 第16题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第17题:

    87 The key ingredient to a successful quality management program are _____.

    A. management's quality philosophy, operational quality assurance and operational quality control. B. quality evaluation methods and functional quality integrators.

    C. technical quality administration, the technical quality specifications, and the quality process review. D. quality evaluation methods, quality progress reviews and the technical quality specifications.

    E. All of the above


    正确答案:A

  • 第18题:

    102 Most quality problems:

    A. originate in the quality department where the ultimate responsibility for quality rests.

    B. originate on the shop floor because of waste and product rework.

    C. are the results of management inattention to potential quality improvement ideas.

    D. could be eliminated if shop supervisors monitored their work more closely.

    E. A and B


    正确答案:C

  • 第19题:

    Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control


    正确答案:D
    执行质量控制(quality control)指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

  • 第20题:

    Performing(74)involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

    A.quality planning

    B.quality assurance

    C.quality performance

    D.quality control


    正确答案:D
    解析:执行质量控制指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

  • 第21题:

    Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

    A.performance

    B.process

    C.product

    D.object


    正确答案:C
    解析:项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

  • 第22题:

    Quality?mangement ensures that an organization,product or service is consitent.It has four main components;quality planing,quality assurance( )and quatily improvenment.

    A.quality obiective
    B.quality policy
    C.quality control
    D.quality system

    答案:C
    解析:

  • 第23题:

    ( )is not included in Control Quality input documents.

    A.Project management plan
    B.Project documents
    C.Quality problems report
    D.Work performance data

    答案:C
    解析:
    质量控制的输入文件不包括:质量问题报告。