niusouti.com

"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .A be completed in reduced overall time than other projects.B be in a higher risk category than other projects.C not be compa

题目

"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

A be completed in reduced overall time than other projects.

B be in a higher risk category than other projects.

C not be compatible with project risk and assessment

D A and B

E All of the above.


相似考题
更多“"Fast-tracked" projects awarded and begun before all planning and risk assessment informat ”相关问题
  • 第1题:

    [A] distributed [B] awarded [C] handed [D] submitted


    正确答案:C

    本题考查通过上下文选择适当动词的能力。空格处填入动词的被动形式,该动作的实际发出者是a press aide,直接宾语是a copy of a press release,间接宾语是Senator Joseph Montoya,含义为“一份新闻稿被新闻助理...给参议员”。由于新闻助理与参议员没有直接的上下级关系,award“授于,判给”、submit“提交,递交”分别表示上对下和下对上的动作,所以[B]、[D]项不正确。又由于文章没有分发新闻稿的语境,所以[A]项distribute“分发,分配”也不能用。只有[C]项hand“交给,递给”符合语意。

  • 第2题:

    A briefing is a short presentation usually given at a meeting or a conference to bring people up to date on business activities , projects , programs or procedures.


    参考答案:简报是一种口头陈述,它通常在开会时用来通报公司最新的活动、项目、计划或程序。

  • 第3题:

    A project is a [temporary] ( ) of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to ( )Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of a(n) ( ) system at a minimum cost within a specified time frame.
    For any systems development project, effective project management is necessary to ensure that the project meets the ( ), is eveloped within an acceptable budget, and fulfills customer expectations and specifications, Project management is a process that starts at the beginning of a project, extends through a project, and doesn't culminate until the project is completed.
    The prerequisite for good project management is a well-defined system development process. Process management is an ongoing activity that documents, manages the use of, and improves an organization s chosen methodology (the"process")for system development, Process management is concemed with the activities, deliverables, and quallty standards to be applled to (请作答此空) project(s).

    A.a single
    B.a particular
    C.some
    D.all

    答案:D
    解析:

  • 第4题:

    ____ at zero, the rate of production tends initially to increase exponentially.

    A: To begin

    B: began

    C: Beginning

    D: Begun


    参考答案:C

  • 第5题:

    A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to(请作答此空)project(s).

    A.a single
    B.a particular
    C.some
    D.all

    答案:D
    解析:
    表示过程管理涉及应用于所有项目的活动。附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。