144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:A.

题目

144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

A. Overhead rates, labor rates and material costs.

B. Overhead rates, schedule slippages, and rework.

C. Rework, cost-of-living adjustments, and overtime.

D. Material costs, shipping cost, and scope changes.

E. Labor rates, material costs, and cost reporting


相似考题
更多“144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:A. ”相关问题
  • 第1题:

    There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.

    A . Management reserve, unplanned allowance fund.

    B . Management reserve, contingency.

    C . Contingency fund, management reserve.

    D . Unplanned allowance fund, budgetary reserve.

    E . Unplanned reserve, planned reserve.


    正确答案:C

  • 第2题:

    The purpose of project Risk Management is to:

    A Identify those factors that will adversely impact project objectives.

    B Assess the impact of adverse project factors.

    C Assess the probability of adverse project factors.

    D A and C

    E All of the above.


    正确答案:E

  • 第3题:

    85 The purpose of project Risk Management is to:

    A. Identify those factors that will adversely impact project objectives.

    B. Assess the impact of adverse project factors.

    C. Assess the probability of adverse project factors.

    D. A and C

    E. All of the above


    正确答案:E

  • 第4题:

    26 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A. Overhead rates, labor rates and material costs.

    B. Overhead rates, schedule slippages, and rework.

    C. Rework, cost-of-living adjustments, and overtime.

    D. Material costs, shipping cost, and scope changes.

    E. Labor rates, material costs, and cost reporting


    正确答案:A

  • 第5题:

    61 Cost and schedule data are usually integrated because:

    A. optimized project cash flow can affect financial requirements

    B. they provide MIS with an integrated system to produce reports

    C. they control escalation allowances

    D. they account for omissions in the definitive estimate

    E. they predict future performance


    正确答案:E

  • 第6题:

    ● The "rolling wave" or "moving window" concept is used most frequently on projects where:

    A The baseline is frozen for the duration of the project and no scope changes are permitted

    B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes

    C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work

    D Networking techniques are not appropriate

    E All of the above


    正确答案:C

  • 第7题:

    ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

    (73)

    A.executive IT manager

    B.project manger

    C.change control board

    D.project sponsor


    正确答案:C
    试题(73)分析
     项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。
    参考答案
    (73)C

  • 第8题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第9题:

    Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( ) is not a project selection method.

    A.Benefit contribution
    B.Expert judgment
    C.Scoring models
    D.Flowcharting

    答案:D
    解析:
    项目选择方法包括测量项目业主的价值和吸引力,并可能包括组织层面其他决策准则。流程图法不是一种项目选择方法。

  • 第10题:

    ( )is a process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

    A.Plan Cost Management
    B.Estimate Costs
    C.Determine Budget
    D.Control Costs

    答案:D
    解析:
    控制成本是一个监控项目状态的过程,目的是更新项目成本并且对成本基准的变化进行管理。

  • 第11题:

    ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis
    B.Qualitative Risk Analysis
    C.Enterprise Environmental Factors
    D.Risk Management Plan

    答案:B
    解析:
    翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

  • 第12题:

    Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

    • A、Benefitcontribution
    • B、Expertjudgment
    • C、Scoringmodels
    • D、Flowcharting

    正确答案:D

  • 第13题:

    Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A . Overhead rates, labor rates and material costs.

    B . Overhead rates, schedule slippages, and rework.

    C . Rework, cost-of-living adjustments, and overtime.

    D . Material costs, shipping cost, and scope changes.

    E . Labor rates, material costs, and cost reporting.


    正确答案:A

  • 第14题:

    19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A. Direct labor dollars

    B. Direct labor hours.

    C. Overhead rates.

    D. Procurement costs.

    E. None of the above


    正确答案:B

  • 第15题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第16题:

    27 The "rolling wave" or "moving window" concept is used most frequently on projects where:

    A. The baseline is frozen for the duration of the project and no scope changes are permitted

    B. Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes

    C. The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work D. Networking techniques are not appropriate

    E. All of the above


    正确答案:C

  • 第17题:

    Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

    A.Benefitcontribution

    B.Expertjudgment

    C.Scoringmodels

    D.Flowcharting


    参考答案:D

  • 第18题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第19题:

    Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. __(71)__ is not a project selection method.

    A.Benefit contribution

    B.Expert judgment

    C.Scoring models

    D.Flowcharting


    正确答案:D
    项目选择方法包括测量项目业主的价值和吸引力,并可能包括组织层面其他决策准则。流程图法不是一种项目选择方法。A.收益分布B.专家判断C.评分模型D.流程图

  • 第20题:

    ● Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. __(74)__ is not a project selection method.

    (74)

    A.Benefit contribution

    B.Expert judgment

    C.Scoring models

    D.Flowcharting


    正确答案:D

  • 第21题:

    Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .

    A.executive IT manager
    B.project manger
    C.change control board
    D.project sponsor

    答案:C
    解析:
    项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73) A.执行经理 B.项目经理 C.变更控制委员会 D.项目发起人

  • 第22题:

    Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .

    A.executive IT manager
    B.project manger
    C.change control board
    D.project sponsor

    答案:C
    解析:
    项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。A. 执行经理 B. 项目经理C. 变更控制委员会 D. 项目发起人

  • 第23题:

    Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

    • A、executive IT manager
    • B、projectmanger
    • C、change control board
    • D、projectsponsor