niusouti.com

Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A . MatrixB . Pure projectC . Project coordinatorD . Project expediterE

题目

Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

A . Matrix

B . Pure project

C . Project coordinator

D . Project expediter

E . Classical/traditional


相似考题
参考答案和解析
正确答案:B
更多“Team members want to work for a project manager that can provide them with career path pla ”相关问题
  • 第1题:

    对于场景:一个公司负责多个项目,每个项目(Project)由一个员工(Employee)团队( Team)来开发。下列UML概念图中,(41)最适合描述这一场景。

    A.图A

    B.图B

    C.图C

    D.图D


    正确答案:B
    本题主要考查类图和多重度的知识。在UML中,关联的多重度是指一个类的实例能够与另一个类的多少个实例相关联。它又称为重复度。多重度表示为一个整数范围n..m,整数n定义所连接的最少对象的数目,而m则为最多对象数(当不知道确切的最大数时,最大数用*号表示)。最常见的多重性有0..1、0..*、1和1..*。在本题中,根据题目的描述,我们不难看出有4个类,而且由描述“一个公司负责多个项目”可知,公司和项目两个类之间的关联是一种一对多的关联,即项目端是多端,这样就可以排除答案C,另外公司和项目之间并不是一种继承的关系,这样就可以排除答案D。而在A和B选项间,他们的区别就在于A的关联牵涉到了3个类,但其实这种表达方式是不存在的,而B选项中很好地表明了题目的意思,即一个项目由一个团队来开发,而团队中的成员个数至少是一个,或者是多个。

  • 第2题:

    Whichactionoccurswhenthepolicymain-policyevaluatestheBGProute10.0.55.2/32?()

    [editpolicy-options]

    policy-statementtest{

    from{

    route-filter10.0.0.016/orlongeraccept;

    route-filter10.0.67.0/24orlangerreject;

    route-filter10.0.0.0/8orlanger;

    }

    then{

    metric10;

    communityaddno-advertise;

    accept;

    }

    }

    policy-statementmain-policy{

    termonly-want-certain-routes{

    from{

    policytest;

    }

    then{

    communityaddharry-402;

    accept;

    }

    }

    }

    communitynoadvertisemembersno-advertise;

    communityharry-402members666:402;

    [editprotocols]

    bgp{

    exportmain-policy;}


    参考答案:B

  • 第3题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。

  • 第4题:

    What defines a BGP confederation?()

    A. autonomous-system 64555;confederation 1111 ;

    B. autonomous-system 64555; confederation 1111 members [ 64555 64777 ];

    C. confederation 64555; autonomous-system 1111 members [ 64555 64777 ];

    D. sub-autonomous-system 64555; confederation 1111 members [ 64555 64777 ];


    参考答案:B

  • 第5题:

    The company has the right to end his employment at any time.

    A:offer
    B:continue
    C:stop
    D:provide

    答案:C
    解析:
    这句话的意思是:公司有权在任何时间终止对他的雇用。句中“end”意为“结束”,四个 选项中A项意为“提出”;B项意为“继续”;C项意为“停止”;D项意为“提供”。因此只有C项最为合适。

  • 第6题:

    已知基类Employee只有一个构造函数,其定义如下: Employee::Employee(int n):id(n){ } Manager是Employee的派生类,则下列对Manager的构造函数的定义中,正确的是?

    A.Manager::Manager(int n):id(n){}

    B.Manager::Manager(int n){id=n;}

    C.Manager::Manager(int n):Employee(n){}

    D.Manager::Manager(int n){Employee(n);}


    Manger::manger(int n):Employee(n){}