When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA.taskB.level of effortC.sub-taskD.projectE.work package

题目

When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A.task

B.level of effort

C.sub-task

D.project

E.work package


相似考题
参考答案和解析
正确答案:E
更多“When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated ”相关问题
  • 第1题:

    A) outset

    B) outbreak

    C) breakthrough

    D) breakdown


    正确答案:B
    答案:B
    [试题分析]近义词辨析题。
    [详细解答]outbreak(爆发;突发)是由动词短语breakout变化而来,the outbreak of World War II即“第二次世界大战的爆发”。其余三项都不合题意。

  • 第2题:

    [A] innate [B] intact [C] integral [D] integrated


    正确答案:C

  • 第3题:

    The work that needs to be accomplished to deliver a product, service, or result with the specified features and functions is called ()。



    A.Scope management
    B.IntegrateD.management
    C.SOW
    D.PMO

    答案:A
    解析:
    译文:为提供有规定特征与功能的产品、服务或成果而需要完成的工作称为()?
    A、范围管理 B、整合管理 C、工作说明书 D、项目管理办公室

  • 第4题:

    PleasechoosethecorrectdescriptionaboutCiscoSelf-DefendingNetworkcharacteristics.()

    A.INTEGRATED-P4S2,COLLABORATIVE-P4S1ADAPTIVE-P4S3

    B.INTEGRATED-P4S1,COLLABORATIVE-P4S2ADAPTIVE-P4S3

    C.INTEGRATED-P4S3,COLLABORATIVE-P4S2ADAPTIVE-P4S1

    D.INTEGRATED-P4S2,COLLABORATIVE-P4S3ADAPTIVE-P4S1


    参考答案:A

  • 第5题:

    The work that needs to be accomplished to deliver a product,service,or result with the specified features and functions is called ( ) .

    A.Scope management
    B.IntegrateD.management
    C.SOW
    D.PMO

    答案:A
    解析:

  • 第6题:

    文化产业项目工作分解结构(work_breakdown_structure,WBS)是文化产业项目范围定义中给出的项目工作范围的描述文件。